Conduit, Furnish & Install, Bridge Mount (Item 0630 2 15): FDOT Unit Price History
11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $49.71/LF
- Contracts (12 mo)
- 11
- Total quantity (12 mo)
- 5,121 LF
- Total amount (12 mo)
- $254,566
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 17 | $53.96 | 34,792 | $1,877,313 |
| 2025 | 2025-01-01 – 2025-12-31 | 23 | $74.89 | 45,226 | $3,387,126 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 11 | $49.71 | 5,121 | $254,566 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 08 | 5 | $40.03 | -19.5% | 1,477 |
| 11 | 1 | $70.25 | +41.3% | 255 |
| 12 | 3 | $44.16 | -11.2% | 2,057 |
| 13 | 2 | $65.09 | +30.9% | 1,332 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0630 2 15 (Conduit, Furnish & Install, Bridge Mount) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $49.71 per LF, on 5,121 LF worth $254,566 in total.
The same report run for earlier periods shows $53.96 in 2024 (17 contracts, 34,792 LF), $74.89 in 2025 (23 contracts, 45,226 LF), $49.71 in the latest 12 months (11 contracts, 5,121 LF). From 2024 to the latest 12 months the weighted average fell 7.9%.
Quantity let statewide shrank 85% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 4 of FDOT's 14 market areas reported this item: area 08 at $40.03 (5 contracts), area 11 at $70.25 (1 contract), area 12 at $44.16 (3 contracts), area 13 at $65.09 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0630: 0630 2 12 Conduit, Furnish & Install, Directional Bore ($34.57 per LF, 171 contracts); 0630 2 11 Conduit, Furnish & Install, Open Trench ($17.21 per LF, 157 contracts); 0630 2 14 Conduit, Furnish & Install, Aboveground ($42.51 per LF, 57 contracts); 0630 2 16 Conduit, Furnish & Install, Embedded Concrete Barriers AND Traffic Railings ($14.04 per LF, 23 contracts); 0630 2 17 Conduit, Furnish & Install, Open Trench Under Pavement ($79.81 per LF, 3 contracts).
Related items in section 0630
- 0630 2 12 · Conduit, Furnish & Install, Directional Bore ($34.57/LF)
- 0630 2 11 · Conduit, Furnish & Install, Open Trench ($17.21/LF)
- 0630 2 14 · Conduit, Furnish & Install, Aboveground ($42.51/LF)
- 0630 2 16 · Conduit, Furnish & Install, Embedded Concrete Barriers AND Traffic Railings ($14.04/LF)
- 0630 2 17 · Conduit, Furnish & Install, Open Trench Under Pavement ($79.81/LF)
- 0630 3 1 · Replace Route Marker FOR Existing Conduit ($248.43/EA)
- 0630 2 18 · Conduit, Furnish & Install, Split Duct ($76.00/LF)
- 0630 2 65 · Conduit, Remove, Bridge Mount ($0.810/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.