Conduit, Furnish & Install, Directional Bore (Item 0630 2 12): FDOT Unit Price History

171 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$34.57/LF
Contracts (12 mo)
171
Total quantity (12 mo)
632,778 LF
Total amount (12 mo)
$21,876,987

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31213$41.76752,917$31,442,387
20252025-01-01 – 2025-12-31194$41.81708,221$29,611,613
Latest 12 months2025-11-01 – 2026-10-31171$34.57632,778$21,876,987

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
018$34.12-1.3%24,489
026$34.87+0.9%3,330
038$40.22+16.3%21,115
044$59.64+72.5%683
0514$32.57-5.8%20,065
0614$28.95-16.3%37,067
0717$55.07+59.3%50,037
0839$37.75+9.2%125,222
093$54.80+58.5%2,617
1011$33.15-4.1%41,262
115$26.34-23.8%27,957
1222$32.87-4.9%184,725
1314$29.90-13.5%55,456
141$25.63-25.9%524

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0630 2 12 (Conduit, Furnish & Install, Directional Bore) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 171 contracts with a quantity-weighted average of $34.57 per LF, on 632,778 LF worth $21,876,987 in total.

The same report run for earlier periods shows $41.76 in 2024 (213 contracts, 752,917 LF), $41.81 in 2025 (194 contracts, 708,221 LF), $34.57 in the latest 12 months (171 contracts, 632,778 LF). From 2024 to the latest 12 months the weighted average fell 17.2%.

Quantity let statewide shrank 16% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 11 had the lowest weighted average ($26.34 per LF, 5 contracts) and market area 04 the highest ($59.64, 4 contracts), 2.3 times as much. Market area 08 let the most contracts with this item (39). 14 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0630: 0630 2 11 Conduit, Furnish & Install, Open Trench ($17.21 per LF, 157 contracts); 0630 2 14 Conduit, Furnish & Install, Aboveground ($42.51 per LF, 57 contracts); 0630 2 16 Conduit, Furnish & Install, Embedded Concrete Barriers AND Traffic Railings ($14.04 per LF, 23 contracts); 0630 2 15 Conduit, Furnish & Install, Bridge Mount ($49.71 per LF, 11 contracts); 0630 2 17 Conduit, Furnish & Install, Open Trench Under Pavement ($79.81 per LF, 3 contracts).

Related items in section 0630

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab