Conduit, Furnish & Install, Open Trench (Item 0630 2 11): FDOT Unit Price History

157 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$17.21/LF
Contracts (12 mo)
157
Total quantity (12 mo)
885,125 LF
Total amount (12 mo)
$15,230,905

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31196$17.24894,794$15,424,049
20252025-01-01 – 2025-12-31194$18.041,238,581$22,341,282
Latest 12 months2025-11-01 – 2026-10-31157$17.21885,125$15,230,905

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
0110$16.39-4.8%22,659
027$18.85+9.5%1,473
039$19.39+12.7%34,092
045$27.18+57.9%718
0515$17.29+0.5%19,993
0613$24.73+43.7%127,695
0717$11.65-32.3%147,867
0838$18.56+7.8%149,201
093$14.72-14.5%6,779
1011$15.86-7.8%17,661
115$14.60-15.2%19,160
1216$17.01-1.2%260,735
133$22.45+30.4%13,081

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0630 2 11 (Conduit, Furnish & Install, Open Trench) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 157 contracts with a quantity-weighted average of $17.21 per LF, on 885,125 LF worth $15,230,905 in total.

The same report run for earlier periods shows $17.24 in 2024 (196 contracts, 894,794 LF), $18.04 in 2025 (194 contracts, 1,238,581 LF), $17.21 in the latest 12 months (157 contracts, 885,125 LF). Across those periods the weighted average stayed within three percent.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 07 had the lowest weighted average ($11.65 per LF, 17 contracts) and market area 04 the highest ($27.18, 5 contracts), 2.3 times as much. Market area 08 let the most contracts with this item (38). 13 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0630: 0630 2 12 Conduit, Furnish & Install, Directional Bore ($34.57 per LF, 171 contracts); 0630 2 14 Conduit, Furnish & Install, Aboveground ($42.51 per LF, 57 contracts); 0630 2 16 Conduit, Furnish & Install, Embedded Concrete Barriers AND Traffic Railings ($14.04 per LF, 23 contracts); 0630 2 15 Conduit, Furnish & Install, Bridge Mount ($49.71 per LF, 11 contracts); 0630 2 17 Conduit, Furnish & Install, Open Trench Under Pavement ($79.81 per LF, 3 contracts).

Related items in section 0630

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.