Shoulder Gutter- Concrete (Item 0520 6): FDOT Unit Price History
32 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $35.05/LF
- Contracts (12 mo)
- 32
- Total quantity (12 mo)
- 84,178 LF
- Total amount (12 mo)
- $2,950,702
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 32 | $39.50 | 81,859 | $3,233,839 |
| 2025 | 2025-01-01 – 2025-12-31 | 43 | $41.27 | 178,357 | $7,360,578 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 32 | $35.05 | 84,178 | $2,950,702 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 3 | $42.37 | +20.9% | 2,106 |
| 02 | 3 | $52.03 | +48.4% | 1,569 |
| 04 | 3 | $57.45 | +63.9% | 3,756 |
| 05 | 1 | $58.48 | +66.8% | 681 |
| 06 | 1 | $65.00 | +85.4% | 40 |
| 07 | 7 | $28.84 | -17.7% | 49,224 |
| 08 | 4 | $49.57 | +41.4% | 2,639 |
| 09 | 3 | $91.53 | +161.1% | 157 |
| 10 | 1 | $213.75 | +509.8% | 58 |
| 11 | 1 | $48.96 | +39.7% | 896 |
| 12 | 5 | $39.06 | +11.4% | 23,052 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0520 6 (Shoulder Gutter- Concrete) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 32 contracts with a quantity-weighted average of $35.05 per LF, on 84,178 LF worth $2,950,702 in total.
The same report run for earlier periods shows $39.50 in 2024 (32 contracts, 81,859 LF), $41.27 in 2025 (43 contracts, 178,357 LF), $35.05 in the latest 12 months (32 contracts, 84,178 LF). From 2024 to the latest 12 months the weighted average fell 11.3%.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 7 market areas with at least three contracts, market area 07 had the lowest weighted average ($28.84 per LF, 7 contracts) and market area 09 the highest ($91.53, 3 contracts), 3.2 times as much. Market area 07 let the most contracts with this item (7). 11 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0520: 0520 1 10 Concrete Curb & Gutter, Type F ($40.38 per LF, 148 contracts); 0520 1 7 Concrete Curb & Gutter, Type E ($36.29 per LF, 70 contracts); 0520 2 4 Concrete Curb, Type D ($36.96 per LF, 50 contracts); 0520 70 Concrete Traffic Separator, Special- Variable Width ($131.63 per SY, 50 contracts); 0520 3 Valley Gutter- Concrete ($50.59 per LF, 28 contracts).
Related items in section 0520
- 0520 1 10 · Concrete Curb & Gutter, Type F ($40.38/LF)
- 0520 1 7 · Concrete Curb & Gutter, Type E ($36.29/LF)
- 0520 2 4 · Concrete Curb, Type D ($36.96/LF)
- 0520 70 · Concrete Traffic Separator, Special- Variable Width ($131.63/SY)
- 0520 3 · Valley Gutter- Concrete ($50.59/LF)
- 0520 5 11 · Traffic Separator Concrete-Type I, 4' Wide ($65.24/LF)
- 0520 5 41 · Traffic Separator Concrete- Type IV, 4' Wide ($80.33/LF)
- 0520 2 2 · Concrete Curb, Type B ($47.93/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.