Traffic Separator Concrete- Type IV, 4' Wide (Item 0520 5 41): FDOT Unit Price History
14 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $80.33/LF
- Contracts (12 mo)
- 14
- Total quantity (12 mo)
- 7,797 LF
- Total amount (12 mo)
- $626,297
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 20 | $74.01 | 4,780 | $353,788 |
| 2025 | 2025-01-01 – 2025-12-31 | 16 | $68.26 | 6,217 | $424,346 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 14 | $80.33 | 7,797 | $626,297 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 07 | 1 | $52.32 | -34.9% | 1,110 |
| 08 | 4 | $107.26 | +33.5% | 652 |
| 10 | 1 | $44.00 | -45.2% | 418 |
| 11 | 1 | $70.36 | -12.4% | 3,375 |
| 12 | 2 | $63.50 | -21% | 447 |
| 13 | 5 | $119.25 | +48.5% | 1,795 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0520 5 41 (Traffic Separator Concrete- Type IV, 4' Wide) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 14 contracts with a quantity-weighted average of $80.33 per LF, on 7,797 LF worth $626,297 in total.
The same report run for earlier periods shows $74.01 in 2024 (20 contracts, 4,780 LF), $68.26 in 2025 (16 contracts, 6,217 LF), $80.33 in the latest 12 months (14 contracts, 7,797 LF). From 2024 to the latest 12 months the weighted average rose 8.5%.
Quantity let statewide grew 63% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 07 at $52.32 (1 contract), area 08 at $107.26 (4 contracts), area 10 at $44.00 (1 contract), area 11 at $70.36 (1 contract), area 12 at $63.50 (2 contracts), area 13 at $119.25 (5 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0520: 0520 1 10 Concrete Curb & Gutter, Type F ($40.38 per LF, 148 contracts); 0520 1 7 Concrete Curb & Gutter, Type E ($36.29 per LF, 70 contracts); 0520 2 4 Concrete Curb, Type D ($36.96 per LF, 50 contracts); 0520 70 Concrete Traffic Separator, Special- Variable Width ($131.63 per SY, 50 contracts); 0520 6 Shoulder Gutter- Concrete ($35.05 per LF, 32 contracts).
Related items in section 0520
- 0520 1 10 · Concrete Curb & Gutter, Type F ($40.38/LF)
- 0520 1 7 · Concrete Curb & Gutter, Type E ($36.29/LF)
- 0520 2 4 · Concrete Curb, Type D ($36.96/LF)
- 0520 70 · Concrete Traffic Separator, Special- Variable Width ($131.63/SY)
- 0520 6 · Shoulder Gutter- Concrete ($35.05/LF)
- 0520 3 · Valley Gutter- Concrete ($50.59/LF)
- 0520 5 11 · Traffic Separator Concrete-Type I, 4' Wide ($65.24/LF)
- 0520 2 2 · Concrete Curb, Type B ($47.93/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.