Concrete Curb & Gutter, Type F (Item 0520 1 10): FDOT Unit Price History
148 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $40.38/LF
- Contracts (12 mo)
- 148
- Total quantity (12 mo)
- 311,054 LF
- Total amount (12 mo)
- $12,559,056
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 190 | $45.83 | 483,599 | $22,163,044 |
| 2025 | 2025-01-01 – 2025-12-31 | 161 | $44.72 | 339,680 | $15,191,971 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 148 | $40.38 | 311,054 | $12,559,056 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 7 | $43.04 | +6.6% | 16,853 |
| 02 | 6 | $59.72 | +47.9% | 1,516 |
| 03 | 7 | $33.61 | -16.8% | 26,255 |
| 04 | 6 | $50.34 | +24.7% | 2,645 |
| 05 | 14 | $52.80 | +30.8% | 14,167 |
| 06 | 14 | $32.59 | -19.3% | 21,460 |
| 07 | 12 | $34.68 | -14.1% | 34,068 |
| 08 | 35 | $40.39 | 0% | 75,942 |
| 09 | 4 | $38.32 | -5.1% | 5,638 |
| 10 | 11 | $40.86 | +1.2% | 10,425 |
| 11 | 1 | $41.17 | +2% | 3,561 |
| 12 | 16 | $35.96 | -10.9% | 52,018 |
| 13 | 15 | $51.01 | +26.3% | 46,506 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0520 1 10 (Concrete Curb & Gutter, Type F) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 148 contracts with a quantity-weighted average of $40.38 per LF, on 311,054 LF worth $12,559,056 in total.
The same report run for earlier periods shows $45.83 in 2024 (190 contracts, 483,599 LF), $44.72 in 2025 (161 contracts, 339,680 LF), $40.38 in the latest 12 months (148 contracts, 311,054 LF). From 2024 to the latest 12 months the weighted average fell 11.9%.
Quantity let statewide shrank 36% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 12 market areas with at least three contracts, market area 06 had the lowest weighted average ($32.59 per LF, 14 contracts) and market area 02 the highest ($59.72, 6 contracts), 1.8 times as much. Market area 08 let the most contracts with this item (35). 13 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0520: 0520 1 7 Concrete Curb & Gutter, Type E ($36.29 per LF, 70 contracts); 0520 2 4 Concrete Curb, Type D ($36.96 per LF, 50 contracts); 0520 70 Concrete Traffic Separator, Special- Variable Width ($131.63 per SY, 50 contracts); 0520 6 Shoulder Gutter- Concrete ($35.05 per LF, 32 contracts); 0520 3 Valley Gutter- Concrete ($50.59 per LF, 28 contracts).
Related items in section 0520
- 0520 1 7 · Concrete Curb & Gutter, Type E ($36.29/LF)
- 0520 2 4 · Concrete Curb, Type D ($36.96/LF)
- 0520 70 · Concrete Traffic Separator, Special- Variable Width ($131.63/SY)
- 0520 6 · Shoulder Gutter- Concrete ($35.05/LF)
- 0520 3 · Valley Gutter- Concrete ($50.59/LF)
- 0520 5 11 · Traffic Separator Concrete-Type I, 4' Wide ($65.24/LF)
- 0520 5 41 · Traffic Separator Concrete- Type IV, 4' Wide ($80.33/LF)
- 0520 2 2 · Concrete Curb, Type B ($47.93/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.