Concrete Curb & Gutter, Type F (Item 0520 1 10): FDOT Unit Price History

148 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$40.38/LF
Contracts (12 mo)
148
Total quantity (12 mo)
311,054 LF
Total amount (12 mo)
$12,559,056

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31190$45.83483,599$22,163,044
20252025-01-01 – 2025-12-31161$44.72339,680$15,191,971
Latest 12 months2025-11-01 – 2026-10-31148$40.38311,054$12,559,056

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
017$43.04+6.6%16,853
026$59.72+47.9%1,516
037$33.61-16.8%26,255
046$50.34+24.7%2,645
0514$52.80+30.8%14,167
0614$32.59-19.3%21,460
0712$34.68-14.1%34,068
0835$40.390%75,942
094$38.32-5.1%5,638
1011$40.86+1.2%10,425
111$41.17+2%3,561
1216$35.96-10.9%52,018
1315$51.01+26.3%46,506

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0520 1 10 (Concrete Curb & Gutter, Type F) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 148 contracts with a quantity-weighted average of $40.38 per LF, on 311,054 LF worth $12,559,056 in total.

The same report run for earlier periods shows $45.83 in 2024 (190 contracts, 483,599 LF), $44.72 in 2025 (161 contracts, 339,680 LF), $40.38 in the latest 12 months (148 contracts, 311,054 LF). From 2024 to the latest 12 months the weighted average fell 11.9%.

Quantity let statewide shrank 36% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 12 market areas with at least three contracts, market area 06 had the lowest weighted average ($32.59 per LF, 14 contracts) and market area 02 the highest ($59.72, 6 contracts), 1.8 times as much. Market area 08 let the most contracts with this item (35). 13 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0520: 0520 1 7 Concrete Curb & Gutter, Type E ($36.29 per LF, 70 contracts); 0520 2 4 Concrete Curb, Type D ($36.96 per LF, 50 contracts); 0520 70 Concrete Traffic Separator, Special- Variable Width ($131.63 per SY, 50 contracts); 0520 6 Shoulder Gutter- Concrete ($35.05 per LF, 32 contracts); 0520 3 Valley Gutter- Concrete ($50.59 per LF, 28 contracts).

Related items in section 0520

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.