Aad Contracting Inc.: TxDOT Bid Results and Margins

Name as published by TxDOT: AAD CONTRACTING INC. · Data as published by TxDOT, lettings Nov 6, 2024 to Mar 19, 2026, retrieved Nov 24, 2026.

Proposals bid
61
Low bids (rank 1)
6
Win rate
9.84%
Low-bid value
$4.4M
Money left on table
$172K
Avg. bid vs. estimate
+10.89%

From Nov 6, 2024 to Mar 19, 2026, Aad Contracting Inc. submitted 61 bids on TxDOT proposals and was the apparent low bidder on 6 of them (9.84%), with low bids totalling $4,386,453. In 6 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $172,187 (3.93% of those bids); the median gap was 3.14%. On average its bids came in 10.89% above TxDOT's engineer's estimate. Its most frequent district was Lufkin (13 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
202410220.0%$1,509,303
202532412.5%$2,877,150
20261900.0%$0

Head-to-head rivals

BidderProposals togetherRanked ahead
Garret Shields Infrastructure3010 of 30
Bk Field Operations LLC234 of 23
Rhino Equity, LLC174 of 17
Structural Integrity Group LLC174 of 17
Icos Management, LLC147 of 14
Premier Contractors LLC104 of 10
Beck-Reit & Sons, Ltd.92 of 9
Lakey, Inc.96 of 9

Districts and work types

DistrictBids
Lufkin13
Paris13
San Antonio9
Dallas7
Bryan6
Work type of low bidsLow bids
Routine Maintenance Project2
Bridge Maintenance1
Bridge Preventative Maintenance - Sealed1
Pedestrian, Sidewalks & Curb Ramps1
Routine Maintenance Project - Sealed1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2024-11-216473-25-001HopkinsGarret Shields Infrastructure$427,200$434,530+1.7%
2026-01-056490-80-001San JacintoRhino Equity, LLC$186,220$191,550+2.9%
2024-11-126400-48-001WalkerGarret Shields Infrastructure$283,536$311,835+10%
2025-10-156491-11-001TrinityAbove All Contracting LLC$169,015$190,624+12.8%
2026-03-186495-72-001TitusCatocon, Inc.$173,785$197,590+13.7%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-03-196496-41-001GraysonRoutine Maintenance Project - Sealed3 of 3$297,000+32.1%-2.3%
2026-03-186481-15-001AtascosaBridge Preventative Maintenance - Sealed5 of 7$175,656+143.3%+70%
2026-03-186493-96-001GuadalupeBridge Preventative Maintenance - Sealed2 of 7$63,916+32.2%+30.7%
2026-03-186495-72-001TitusRoutine Maintenance Project2 of 2$197,590+13.7%+8.1%
2026-03-106493-02-001Fort BendBridge Preventative Maintenance - Sealed2 of 5$421,575+28%+20.6%
2026-02-196492-30-001HuntRoutine Maintenance Project - Sealed4 of 4$1,204,275+98.3%+26.2%
2026-02-186488-07-001TrinityRoutine Maintenance Project - Sealed3 of 8$279,315-5.9%-60.2%
2026-02-116485-65-001ArcherRoutine Maintenance Project - Sealed5 of 7$322,919+11.8%+4.4%
2026-02-116491-01-001NacogdochesRoutine Maintenance Project - Sealed5 of 5$199,034+32%+34.2%
2026-02-106494-76-001WalkerRoutine Maintenance Project - Sealed5 of 7$100,000+73.9%-1.5%
2026-02-106496-30-001BrazosRoutine Maintenance Project - Sealed3 of 4$654,825+23.6%+53.7%
2026-02-040901-00-067LamarPedestrian, Sidewalks & Curb Ramps5 of 13$818,260+12.5%-8.9%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.