Catocon, Inc.: TxDOT Bid Results and Margins

Name as published by TxDOT: CATOCON, INC. · Data as published by TxDOT, lettings Nov 13, 2024 to Nov 19, 2026, retrieved Nov 24, 2026.

Proposals bid
52
Low bids (rank 1)
13
Win rate
25%
Low-bid value
$4.9M
Money left on table
$460K
Avg. bid vs. estimate
+2.71%

From Nov 13, 2024 to Nov 19, 2026, Catocon, Inc. submitted 52 bids on TxDOT proposals and was the apparent low bidder on 13 of them (25%), with low bids totalling $4,919,582. In 10 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $459,576 (14.62% of those bids); the median gap was 9.31%. On average its bids came in 2.71% above TxDOT's engineer's estimate. Its most frequent district was Paris (27 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
2024700.0%$0
202523417.4%$1,760,861
202622940.9%$3,158,720

Head-to-head rivals

BidderProposals togetherRanked ahead
Rhino Equity, LLC196 of 19
S Fowler Services LLC1610 of 16
Cehand Services LLC134 of 13
Cross Plus Construction, LLC106 of 10
Western Certified Arborists109 of 10
Austin Barricade Company, L.L.C.95 of 9
Mercer Tree Service96 of 9
H. V. Caver, Inc.73 of 7

Districts and work types

DistrictBids
Paris27
Atlanta14
Tyler9
Abilene1
Dallas1
Work type of low bidsLow bids
Routine Maintenance Project - Sealed8
Routine Maintenance Project4
Bridge Preventative Maintenance - Sealed1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2024-11-216473-99-001LamarMercer Tree Service$200,825$215,909+7.5%
2026-11-196510-23-001LamarAustin Barricade Company, L.L.C.$328,899$354,575+7.8%
2026-05-216500-15-001LamarMercer Tree Service$212,515$235,087+10.6%
2025-02-206476-97-001UpshurRhino Equity, LLC$420,697$515,687+22.6%
2025-08-216483-72-001FanninAwp Safety$445,800$579,150+29.9%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-196510-23-001LamarRoutine Maintenance Project - Sealed2 of 2$354,575+7.8%+11.7%
2026-09-176503-98-001HuntRoutine Maintenance Project - Sealed6 of 8$360,012+31.9%+3.2%
2026-09-176505-02-001HopkinsRoutine Maintenance Project - Sealed2 of 6$158,681+84.7%+21.2%
2026-09-176505-03-001HopkinsRoutine Maintenance Project - Sealed1 of 7$388,271—-26.7%
2026-08-206502-67-001HuntRoutine Maintenance Project - Sealed3 of 3$737,200+93.9%+12%
2026-07-156502-09-001CassRoutine Maintenance Project1 of 3$673,520—-29.5%
2026-07-156502-12-001MarionRoutine Maintenance Project3 of 6$361,541+6.7%-22.9%
2026-07-026502-10-001UpshurRoutine Maintenance Project3 of 6$864,811+13.3%-17%
2026-07-026503-33-001LamarRoutine Maintenance Project - Sealed3 of 3$2,827,500+51.4%+78.7%
2026-05-216500-15-001LamarRoutine Maintenance Project - Sealed2 of 5$235,087+10.6%-11.7%
2026-05-126493-93-001WoodRoutine Maintenance Project - Sealed1 of 1$330,480—+3.6%
2026-05-126500-52-001SmithRoutine Maintenance Project - Sealed1 of 1$631,830—+11.1%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.