Multi-Column Ground Sign Assembly, Relocate (Item 0700 2500): FDOT Unit Price History
18 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $4,362.14/EA
- Contracts (12 mo)
- 18
- Total quantity (12 mo)
- 54 EA
- Total amount (12 mo)
- $235,556
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 17 | $7,568.67 | 28 | $211,923 |
| 2025 | 2025-01-01 – 2025-12-31 | 36 | $9,240.57 | 125 | $1,155,071 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 18 | $4,362.14 | 54 | $235,556 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $1,381.26 | -68.3% | 10 |
| 03 | 1 | $6,960.00 | +59.6% | 2 |
| 05 | 1 | $12,310.00 | +182.2% | 3 |
| 07 | 4 | $4,108.80 | -5.8% | 10 |
| 08 | 6 | $6,397.93 | +46.7% | 8 |
| 12 | 4 | $3,743.89 | -14.2% | 21 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0700 2500 (Multi-Column Ground Sign Assembly, Relocate) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 18 contracts with a quantity-weighted average of $4,362.14 per EA, on 54 EA worth $235,556 in total.
The same report run for earlier periods shows $7,568.67 in 2024 (17 contracts, 28 EA), $9,240.57 in 2025 (36 contracts, 125 EA), $4,362.14 in the latest 12 months (18 contracts, 54 EA). From 2024 to the latest 12 months the weighted average fell 42.4%.
Quantity let statewide grew 93% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 12 had the lowest weighted average ($3,743.89 per EA, 4 contracts) and market area 08 the highest ($6,397.93, 6 contracts), 1.7 times as much. Market area 08 let the most contracts with this item (6). 6 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0700: 0700 1111 Single Column Ground Sign Assembly, F&I Ground Mount, Less Than 12 SF ($562.79 per EA, 199 contracts); 0700 1600 Single Column Ground Sign Assembly, Remove ($53.69 per EA, 193 contracts); 0700 1112 Single Column Ground Sign Assembly, F&I Ground Mount, 12.0-20.0 SF ($2,123.77 per EA, 147 contracts); 0700 1500 Single Column Ground Sign Assembly, Relocate ($371.65 per EA, 121 contracts); 0700 13 15 Retroreflective Sign Strip- Furnish AND Install, 5' ($102.80 per EA, 108 contracts).
Related items in section 0700
- 0700 1111 · Single Column Ground Sign Assembly, F&I Ground Mount, Less Than 12 SF ($562.79/EA)
- 0700 1600 · Single Column Ground Sign Assembly, Remove ($53.69/EA)
- 0700 1112 · Single Column Ground Sign Assembly, F&I Ground Mount, 12.0-20.0 SF ($2,123.77/EA)
- 0700 1500 · Single Column Ground Sign Assembly, Relocate ($371.65/EA)
- 0700 13 15 · Retroreflective Sign Strip- Furnish AND Install, 5' ($102.80/EA)
- 0700 3601 · Sign Panel, Remove, UP TO 12 SF ($55.04/EA)
- 0700 1113 · Single Column Ground Sign Assembly, F&I Ground Mount, 20.1-30.0 SF ($2,552.63/EA)
- 0700 3101 · Sign Panel, Furnish & Install Ground Mount, UP TO 12 SF ($299.75/EA)