Single Column Ground Sign Assembly, F&I Ground Mount, 20.1-30.0 SF (Item 0700 1113): FDOT Unit Price History

73 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$2,552.63/EA
Contracts (12 mo)
73
Total quantity (12 mo)
471 EA
Total amount (12 mo)
$1,202,290

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3182$2,511.23678$1,702,617
20252025-01-01 – 2025-12-3199$2,535.61594$1,506,151
Latest 12 months2025-11-01 – 2026-10-3173$2,552.63471$1,202,290

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$2,300.00-9.9%4
033$2,278.15-10.8%32
044$2,600.28+1.9%4
052$2,936.15+15%13
067$2,704.04+5.9%26
0713$3,271.30+28.2%53
0815$2,320.44-9.1%197
093$2,555.13+0.1%25
106$2,740.77+7.4%24
111$2,660.00+4.2%2
129$2,605.97+2.1%43
139$2,578.64+1%48

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0700 1113 (Single Column Ground Sign Assembly, F&I Ground Mount, 20.1-30.0 SF) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 73 contracts with a quantity-weighted average of $2,552.63 per EA, on 471 EA worth $1,202,290 in total.

The same report run for earlier periods shows $2,511.23 in 2024 (82 contracts, 678 EA), $2,535.61 in 2025 (99 contracts, 594 EA), $2,552.63 in the latest 12 months (73 contracts, 471 EA). Across those periods the weighted average stayed within three percent.

Quantity let statewide shrank 31% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 9 market areas with at least three contracts, market area 03 had the lowest weighted average ($2,278.15 per EA, 3 contracts) and market area 07 the highest ($3,271.30, 13 contracts), 1.4 times as much. Market area 08 let the most contracts with this item (15). 12 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0700: 0700 1111 Single Column Ground Sign Assembly, F&I Ground Mount, Less Than 12 SF ($562.79 per EA, 199 contracts); 0700 1600 Single Column Ground Sign Assembly, Remove ($53.69 per EA, 193 contracts); 0700 1112 Single Column Ground Sign Assembly, F&I Ground Mount, 12.0-20.0 SF ($2,123.77 per EA, 147 contracts); 0700 1500 Single Column Ground Sign Assembly, Relocate ($371.65 per EA, 121 contracts); 0700 13 15 Retroreflective Sign Strip- Furnish AND Install, 5' ($102.80 per EA, 108 contracts).

Related items in section 0700

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.