Single Column Ground Sign Assembly, F&I Ground Mount, Less Than 12 SF (Item 0700 1111): FDOT Unit Price History
199 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $562.79/EA
- Contracts (12 mo)
- 199
- Total quantity (12 mo)
- 7,809 EA
- Total amount (12 mo)
- $4,394,825
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 210 | $527.99 | 11,691 | $6,172,716 |
| 2025 | 2025-01-01 – 2025-12-31 | 236 | $589.38 | 9,596 | $5,655,714 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 199 | $562.79 | 7,809 | $4,394,825 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 10 | $628.68 | +11.7% | 245 |
| 02 | 10 | $534.26 | -5.1% | 178 |
| 03 | 12 | $484.34 | -13.9% | 502 |
| 04 | 15 | $504.50 | -10.4% | 634 |
| 05 | 19 | $513.06 | -8.8% | 595 |
| 06 | 16 | $543.11 | -3.5% | 692 |
| 07 | 20 | $598.94 | +6.4% | 956 |
| 08 | 43 | $543.90 | -3.4% | 1,854 |
| 09 | 5 | $602.56 | +7.1% | 195 |
| 10 | 12 | $624.58 | +11% | 508 |
| 11 | 4 | $480.13 | -14.7% | 239 |
| 12 | 17 | $603.42 | +7.2% | 404 |
| 13 | 15 | $654.22 | +16.2% | 796 |
| 14 | 1 | $595.00 | +5.7% | 11 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0700 1111 (Single Column Ground Sign Assembly, F&I Ground Mount, Less Than 12 SF) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 199 contracts with a quantity-weighted average of $562.79 per EA, on 7,809 EA worth $4,394,825 in total.
The same report run for earlier periods shows $527.99 in 2024 (210 contracts, 11,691 EA), $589.38 in 2025 (236 contracts, 9,596 EA), $562.79 in the latest 12 months (199 contracts, 7,809 EA). From 2024 to the latest 12 months the weighted average rose 6.6%.
Quantity let statewide shrank 33% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 11 had the lowest weighted average ($480.13 per EA, 4 contracts) and market area 13 the highest ($654.22, 15 contracts), 1.4 times as much. Market area 08 let the most contracts with this item (43). 14 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0700: 0700 1600 Single Column Ground Sign Assembly, Remove ($53.69 per EA, 193 contracts); 0700 1112 Single Column Ground Sign Assembly, F&I Ground Mount, 12.0-20.0 SF ($2,123.77 per EA, 147 contracts); 0700 1500 Single Column Ground Sign Assembly, Relocate ($371.65 per EA, 121 contracts); 0700 13 15 Retroreflective Sign Strip- Furnish AND Install, 5' ($102.80 per EA, 108 contracts); 0700 3601 Sign Panel, Remove, UP TO 12 SF ($55.04 per EA, 83 contracts).
Related items in section 0700
- 0700 1600 · Single Column Ground Sign Assembly, Remove ($53.69/EA)
- 0700 1112 · Single Column Ground Sign Assembly, F&I Ground Mount, 12.0-20.0 SF ($2,123.77/EA)
- 0700 1500 · Single Column Ground Sign Assembly, Relocate ($371.65/EA)
- 0700 13 15 · Retroreflective Sign Strip- Furnish AND Install, 5' ($102.80/EA)
- 0700 3601 · Sign Panel, Remove, UP TO 12 SF ($55.04/EA)
- 0700 1113 · Single Column Ground Sign Assembly, F&I Ground Mount, 20.1-30.0 SF ($2,552.63/EA)
- 0700 3101 · Sign Panel, Furnish & Install Ground Mount, UP TO 12 SF ($299.75/EA)
- 0700 2600 · Multi-Column Ground Sign Assembly, Remove ($1,132.48/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.