Electrical Power Service- Transformer, F&I, 5-10 KVA, Single Phase, Copper Windings (Item 0639 6121): FDOT Unit Price History
14 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $3,384.13/EA
- Contracts (12 mo)
- 14
- Total quantity (12 mo)
- 104 EA
- Total amount (12 mo)
- $351,950
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 16 | $3,153.63 | 82 | $258,598 |
| 2025 | 2025-01-01 – 2025-12-31 | 21 | $2,723.14 | 178 | $484,720 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 14 | $3,384.13 | 104 | $351,950 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 1 | $4,780.18 | +41.3% | 4 |
| 05 | 1 | $3,664.00 | +8.3% | 9 |
| 06 | 1 | $3,048.00 | -9.9% | 4 |
| 07 | 1 | $3,200.00 | -5.4% | 10 |
| 08 | 4 | $2,960.57 | -12.5% | 16 |
| 11 | 1 | $3,803.08 | +12.4% | 1 |
| 12 | 4 | $3,283.02 | -3% | 35 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0639 6121 (Electrical Power Service- Transformer, F&I, 5-10 KVA, Single Phase, Copper Windings) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 14 contracts with a quantity-weighted average of $3,384.13 per EA, on 104 EA worth $351,950 in total.
The same report run for earlier periods shows $3,153.63 in 2024 (16 contracts, 82 EA), $2,723.14 in 2025 (21 contracts, 178 EA), $3,384.13 in the latest 12 months (14 contracts, 104 EA). From 2024 to the latest 12 months the weighted average rose 7.3%.
Quantity let statewide grew 27% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 03 at $4,780.18 (1 contract), area 05 at $3,664.00 (1 contract), area 06 at $3,048.00 (1 contract), area 07 at $3,200.00 (1 contract), area 08 at $2,960.57 (4 contracts), area 11 at $3,803.08 (1 contract), area 12 at $3,283.02 (4 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0639: 0639 2 1 Electrical Service Wire, Furnish & Install ($13.20 per LF, 108 contracts); 0639 1122 Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22 per AS, 84 contracts); 0639 3 11 Electrical Service Disconnect, F&I, Pole Mount ($2,738.60 per EA, 62 contracts); 0639 2 6 Electrical Service Wire, Remove ($1.33 per LF, 50 contracts); 0639 1620 Electrical Power Service, Remove Underground ($990.24 per AS, 32 contracts).
Related items in section 0639
- 0639 2 1 · Electrical Service Wire, Furnish & Install ($13.20/LF)
- 0639 1122 · Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22/AS)
- 0639 3 11 · Electrical Service Disconnect, F&I, Pole Mount ($2,738.60/EA)
- 0639 2 6 · Electrical Service Wire, Remove ($1.33/LF)
- 0639 1620 · Electrical Power Service, Remove Underground ($990.24/AS)
- 0639 8130 · Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13/LS)
- 0639 3 60 · Electrical Service Disconnect, Remove- Pole OR Cabinet TO Remain ($649.58/EA)
- 0639 1610 · Electrical Power Service, Remove Overhead ($629.48/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.