Electrical Service Disconnect, Remove- Pole OR Cabinet TO Remain (Item 0639 3 60): FDOT Unit Price History
27 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $649.58/EA
- Contracts (12 mo)
- 27
- Total quantity (12 mo)
- 73 EA
- Total amount (12 mo)
- $47,420
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 33 | $976.40 | 81 | $79,089 |
| 2025 | 2025-01-01 – 2025-12-31 | 22 | $590.63 | 103 | $60,835 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 27 | $649.58 | 73 | $47,420 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 2 | $170.82 | -73.7% | 3 |
| 05 | 3 | $452.50 | -30.3% | 3 |
| 06 | 1 | $493.00 | -24.1% | 2 |
| 07 | 2 | $494.43 | -23.9% | 3 |
| 08 | 5 | $641.80 | -1.2% | 21 |
| 11 | 2 | $284.09 | -56.3% | 3 |
| 12 | 8 | $676.24 | +4.1% | 28 |
| 13 | 4 | $981.57 | +51.1% | 10 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0639 3 60 (Electrical Service Disconnect, Remove- Pole OR Cabinet TO Remain) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 27 contracts with a quantity-weighted average of $649.58 per EA, on 73 EA worth $47,420 in total.
The same report run for earlier periods shows $976.40 in 2024 (33 contracts, 81 EA), $590.63 in 2025 (22 contracts, 103 EA), $649.58 in the latest 12 months (27 contracts, 73 EA). From 2024 to the latest 12 months the weighted average fell 33.5%.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 4 market areas with at least three contracts, market area 05 had the lowest weighted average ($452.50 per EA, 3 contracts) and market area 13 the highest ($981.57, 4 contracts), 2.2 times as much. Market area 12 let the most contracts with this item (8). 8 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0639: 0639 2 1 Electrical Service Wire, Furnish & Install ($13.20 per LF, 108 contracts); 0639 1122 Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22 per AS, 84 contracts); 0639 3 11 Electrical Service Disconnect, F&I, Pole Mount ($2,738.60 per EA, 62 contracts); 0639 2 6 Electrical Service Wire, Remove ($1.33 per LF, 50 contracts); 0639 1620 Electrical Power Service, Remove Underground ($990.24 per AS, 32 contracts).
Related items in section 0639
- 0639 2 1 · Electrical Service Wire, Furnish & Install ($13.20/LF)
- 0639 1122 · Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22/AS)
- 0639 3 11 · Electrical Service Disconnect, F&I, Pole Mount ($2,738.60/EA)
- 0639 2 6 · Electrical Service Wire, Remove ($1.33/LF)
- 0639 1620 · Electrical Power Service, Remove Underground ($990.24/AS)
- 0639 8130 · Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13/LS)
- 0639 1610 · Electrical Power Service, Remove Overhead ($629.48/AS)
- 0639 6121 · Electrical Power Service- Transformer, F&I, 5-10 KVA, Single Phase, Copper Windings ($3,384.13/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.