Electrical Service Disconnect, F&I, Pole Mount (Item 0639 3 11): FDOT Unit Price History
62 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $2,738.60/EA
- Contracts (12 mo)
- 62
- Total quantity (12 mo)
- 316 EA
- Total amount (12 mo)
- $865,399
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 97 | $2,825.07 | 522 | $1,474,688 |
| 2025 | 2025-01-01 – 2025-12-31 | 89 | $2,725.70 | 698 | $1,902,539 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 62 | $2,738.60 | 316 | $865,399 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $950.00 | -65.3% | 2 |
| 02 | 1 | $1,000.00 | -63.5% | 1 |
| 03 | 4 | $1,128.97 | -58.8% | 11 |
| 04 | 1 | $4,325.71 | +58% | 1 |
| 05 | 4 | $1,964.34 | -28.3% | 17 |
| 06 | 4 | $3,120.00 | +13.9% | 36 |
| 07 | 4 | $3,107.10 | +13.5% | 33 |
| 08 | 18 | $2,703.22 | -1.3% | 60 |
| 10 | 3 | $1,529.23 | -44.2% | 17 |
| 11 | 4 | $3,398.61 | +24.1% | 12 |
| 12 | 13 | $3,084.23 | +12.6% | 98 |
| 13 | 2 | $3,500.00 | +27.8% | 3 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0639 3 11 (Electrical Service Disconnect, F&I, Pole Mount) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 62 contracts with a quantity-weighted average of $2,738.60 per EA, on 316 EA worth $865,399 in total.
The same report run for earlier periods shows $2,825.07 in 2024 (97 contracts, 522 EA), $2,725.70 in 2025 (89 contracts, 698 EA), $2,738.60 in the latest 12 months (62 contracts, 316 EA). From 2024 to the latest 12 months the weighted average fell 3.1%.
Quantity let statewide shrank 39% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 8 market areas with at least three contracts, market area 03 had the lowest weighted average ($1,128.97 per EA, 4 contracts) and market area 11 the highest ($3,398.61, 4 contracts), 3.0 times as much. Market area 08 let the most contracts with this item (18). 12 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0639: 0639 2 1 Electrical Service Wire, Furnish & Install ($13.20 per LF, 108 contracts); 0639 1122 Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22 per AS, 84 contracts); 0639 2 6 Electrical Service Wire, Remove ($1.33 per LF, 50 contracts); 0639 1620 Electrical Power Service, Remove Underground ($990.24 per AS, 32 contracts); 0639 8130 Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13 per LS, 30 contracts).
Related items in section 0639
- 0639 2 1 · Electrical Service Wire, Furnish & Install ($13.20/LF)
- 0639 1122 · Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22/AS)
- 0639 2 6 · Electrical Service Wire, Remove ($1.33/LF)
- 0639 1620 · Electrical Power Service, Remove Underground ($990.24/AS)
- 0639 8130 · Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13/LS)
- 0639 3 60 · Electrical Service Disconnect, Remove- Pole OR Cabinet TO Remain ($649.58/EA)
- 0639 1610 · Electrical Power Service, Remove Overhead ($629.48/AS)
- 0639 6121 · Electrical Power Service- Transformer, F&I, 5-10 KVA, Single Phase, Copper Windings ($3,384.13/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.