Electrical Service Wire, Furnish & Install (Item 0639 2 1): FDOT Unit Price History
108 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $13.20/LF
- Contracts (12 mo)
- 108
- Total quantity (12 mo)
- 355,362 LF
- Total amount (12 mo)
- $4,691,294
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 149 | $10.33 | 378,453 | $3,911,302 |
| 2025 | 2025-01-01 – 2025-12-31 | 135 | $15.51 | 534,623 | $8,290,918 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 108 | $13.20 | 355,362 | $4,691,294 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 5 | $4.90 | -62.9% | 1,585 |
| 02 | 2 | $6.86 | -48% | 231 |
| 03 | 5 | $8.94 | -32.3% | 6,495 |
| 04 | 2 | $8.97 | -32% | 208 |
| 05 | 4 | $9.32 | -29.4% | 10,649 |
| 06 | 8 | $11.70 | -11.4% | 25,137 |
| 07 | 8 | $13.23 | +0.2% | 34,557 |
| 08 | 25 | $14.91 | +13% | 50,614 |
| 09 | 1 | $22.00 | +66.7% | 14 |
| 10 | 7 | $12.96 | -1.8% | 1,689 |
| 11 | 4 | $13.38 | +1.4% | 2,717 |
| 12 | 20 | $14.57 | +10.4% | 182,410 |
| 13 | 13 | $12.06 | -8.6% | 13,924 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0639 2 1 (Electrical Service Wire, Furnish & Install) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 108 contracts with a quantity-weighted average of $13.20 per LF, on 355,362 LF worth $4,691,294 in total.
The same report run for earlier periods shows $10.33 in 2024 (149 contracts, 378,453 LF), $15.51 in 2025 (135 contracts, 534,623 LF), $13.20 in the latest 12 months (108 contracts, 355,362 LF). From 2024 to the latest 12 months the weighted average rose 27.8%.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 10 market areas with at least three contracts, market area 01 had the lowest weighted average ($4.90 per LF, 5 contracts) and market area 08 the highest ($14.91, 25 contracts), 3.0 times as much. Market area 08 let the most contracts with this item (25). 13 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0639: 0639 1122 Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22 per AS, 84 contracts); 0639 3 11 Electrical Service Disconnect, F&I, Pole Mount ($2,738.60 per EA, 62 contracts); 0639 2 6 Electrical Service Wire, Remove ($1.33 per LF, 50 contracts); 0639 1620 Electrical Power Service, Remove Underground ($990.24 per AS, 32 contracts); 0639 8130 Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13 per LS, 30 contracts).
Related items in section 0639
- 0639 1122 · Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22/AS)
- 0639 3 11 · Electrical Service Disconnect, F&I, Pole Mount ($2,738.60/EA)
- 0639 2 6 · Electrical Service Wire, Remove ($1.33/LF)
- 0639 1620 · Electrical Power Service, Remove Underground ($990.24/AS)
- 0639 8130 · Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13/LS)
- 0639 3 60 · Electrical Service Disconnect, Remove- Pole OR Cabinet TO Remain ($649.58/EA)
- 0639 1610 · Electrical Power Service, Remove Overhead ($629.48/AS)
- 0639 6121 · Electrical Power Service- Transformer, F&I, 5-10 KVA, Single Phase, Copper Windings ($3,384.13/EA)