Electrical Power Service, F&I, Underground, Meter NOT Required (Item 0639 1123): FDOT Unit Price History
13 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AS
- Weighted average (12 mo)
- $19,437.43/AS
- Contracts (12 mo)
- 13
- Total quantity (12 mo)
- 81 AS
- Total amount (12 mo)
- $1,574,432
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 6 | $5,368.24 | 10 | $53,682 |
| 2025 | 2025-01-01 – 2025-12-31 | 5 | $7,163.78 | 10 | $71,638 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 13 | $19,437.43 | 81 | $1,574,432 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 05 | 2 | $4,311.80 | -77.8% | 2 |
| 06 | 2 | $22,940.83 | +18% | 63 |
| 07 | 1 | $4,339.01 | -77.7% | 3 |
| 08 | 1 | $21,068.48 | +8.4% | 2 |
| 12 | 3 | $5,015.67 | -74.2% | 5 |
| 13 | 4 | $6,717.29 | -65.4% | 6 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0639 1123 (Electrical Power Service, F&I, Underground, Meter NOT Required) is measured in AS. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 13 contracts with a quantity-weighted average of $19,437.43 per AS, on 81 AS worth $1,574,432 in total.
The same report run for earlier periods shows $5,368.24 in 2024 (6 contracts, 10 AS), $7,163.78 in 2025 (5 contracts, 10 AS), $19,437.43 in the latest 12 months (13 contracts, 81 AS). From 2024 to the latest 12 months the weighted average rose 262.1%.
Quantity let statewide grew 710% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 05 at $4,311.80 (2 contracts), area 06 at $22,940.83 (2 contracts), area 07 at $4,339.01 (1 contract), area 08 at $21,068.48 (1 contract), area 12 at $5,015.67 (3 contracts), area 13 at $6,717.29 (4 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0639: 0639 2 1 Electrical Service Wire, Furnish & Install ($13.20 per LF, 108 contracts); 0639 1122 Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22 per AS, 84 contracts); 0639 3 11 Electrical Service Disconnect, F&I, Pole Mount ($2,738.60 per EA, 62 contracts); 0639 2 6 Electrical Service Wire, Remove ($1.33 per LF, 50 contracts); 0639 1620 Electrical Power Service, Remove Underground ($990.24 per AS, 32 contracts).
Related items in section 0639
- 0639 2 1 · Electrical Service Wire, Furnish & Install ($13.20/LF)
- 0639 1122 · Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22/AS)
- 0639 3 11 · Electrical Service Disconnect, F&I, Pole Mount ($2,738.60/EA)
- 0639 2 6 · Electrical Service Wire, Remove ($1.33/LF)
- 0639 1620 · Electrical Power Service, Remove Underground ($990.24/AS)
- 0639 8130 · Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13/LS)
- 0639 3 60 · Electrical Service Disconnect, Remove- Pole OR Cabinet TO Remain ($649.58/EA)
- 0639 1610 · Electrical Power Service, Remove Overhead ($629.48/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.