Electrical Power Service, F&I, Underground, Meter Furnished BY Power Company (Item 0639 1121): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AS
- Weighted average (12 mo)
- $9,854.24/AS
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 29 AS
- Total amount (12 mo)
- $285,773
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 14 | $5,417.42 | 24 | $130,018 |
| 2025 | 2025-01-01 – 2025-12-31 | 8 | $8,503.96 | 20 | $170,079 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $9,854.24 | 29 | $285,773 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 2 | $2,808.96 | -71.5% | 2 |
| 06 | 1 | $13,732.33 | +39.4% | 3 |
| 08 | 5 | $10,625.09 | +7.8% | 13 |
| 12 | 1 | $5,824.05 | -40.9% | 1 |
| 13 | 3 | $9,500.77 | -3.6% | 10 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0639 1121 (Electrical Power Service, F&I, Underground, Meter Furnished BY Power Company) is measured in AS. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $9,854.24 per AS, on 29 AS worth $285,773 in total.
The same report run for earlier periods shows $5,417.42 in 2024 (14 contracts, 24 AS), $8,503.96 in 2025 (8 contracts, 20 AS), $9,854.24 in the latest 12 months (12 contracts, 29 AS). From 2024 to the latest 12 months the weighted average rose 81.9%.
Quantity let statewide grew 21% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 03 at $2,808.96 (2 contracts), area 06 at $13,732.33 (1 contract), area 08 at $10,625.09 (5 contracts), area 12 at $5,824.05 (1 contract), area 13 at $9,500.77 (3 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0639: 0639 2 1 Electrical Service Wire, Furnish & Install ($13.20 per LF, 108 contracts); 0639 1122 Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22 per AS, 84 contracts); 0639 3 11 Electrical Service Disconnect, F&I, Pole Mount ($2,738.60 per EA, 62 contracts); 0639 2 6 Electrical Service Wire, Remove ($1.33 per LF, 50 contracts); 0639 1620 Electrical Power Service, Remove Underground ($990.24 per AS, 32 contracts).
Related items in section 0639
- 0639 2 1 · Electrical Service Wire, Furnish & Install ($13.20/LF)
- 0639 1122 · Electrical Power Service, F&I, Underground, Meter Purchased BY Contractor ($5,545.22/AS)
- 0639 3 11 · Electrical Service Disconnect, F&I, Pole Mount ($2,738.60/EA)
- 0639 2 6 · Electrical Service Wire, Remove ($1.33/LF)
- 0639 1620 · Electrical Power Service, Remove Underground ($990.24/AS)
- 0639 8130 · Electrical Power Service- Contribution IN AID OF Construction (Ciac), FPL (DO NOT BID) ($136,448.13/LS)
- 0639 3 60 · Electrical Service Disconnect, Remove- Pole OR Cabinet TO Remain ($649.58/EA)
- 0639 1610 · Electrical Power Service, Remove Overhead ($629.48/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.