Junction BOX, Furnish & Install, Mounted (Item 0635 3 12): FDOT Unit Price History

15 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$851.16/EA
Contracts (12 mo)
15
Total quantity (12 mo)
165 EA
Total amount (12 mo)
$140,441

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3114$913.96136$124,299
20252025-01-01 – 2025-12-3121$1,278.85211$269,837
Latest 12 months2025-11-01 – 2026-10-3115$851.16165$140,441

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
031$157.00-81.6%2
072$684.39-19.6%49
083$867.26+1.9%13
111$1,000.00+17.5%20
126$897.84+5.5%71
132$1,157.15+35.9%10

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0635 3 12 (Junction BOX, Furnish & Install, Mounted) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 15 contracts with a quantity-weighted average of $851.16 per EA, on 165 EA worth $140,441 in total.

The same report run for earlier periods shows $913.96 in 2024 (14 contracts, 136 EA), $1,278.85 in 2025 (21 contracts, 211 EA), $851.16 in the latest 12 months (15 contracts, 165 EA). From 2024 to the latest 12 months the weighted average fell 6.9%.

Quantity let statewide grew 21% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 03 at $157.00 (1 contract), area 07 at $684.39 (2 contracts), area 08 at $867.26 (3 contracts), area 11 at $1,000.00 (1 contract), area 12 at $897.84 (6 contracts), area 13 at $1,157.15 (2 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0635: 0635 2 11 Pull & Splice BOX, F&I, 13" X 24" Cover Size ($1,430.96 per EA, 168 contracts); 0635 2 12 Pull & Splice BOX, F&I, 24" X 36" Cover Size ($2,733.97 per EA, 77 contracts); 0635 2 14 Pull & Splice BOX, F&I, 17" X 30" Cover Size ($1,763.94 per EA, 40 contracts); 0635 2 13 Pull & Splice BOX, F&I, 30" X 60" Rectangular OR 36" Round Cover Size ($5,683.80 per EA, 39 contracts); 0635 3 13 Junction BOX, Furnish & Install, Embedded ($1,096.34 per EA, 23 contracts).

Related items in section 0635

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.