Pull & Splice BOX, Install (Item 0635 2 30): FDOT Unit Price History
19 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $1,087.37/EA
- Contracts (12 mo)
- 19
- Total quantity (12 mo)
- 89 EA
- Total amount (12 mo)
- $96,776
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 13 | $1,624.77 | 113 | $183,600 |
| 2025 | 2025-01-01 – 2025-12-31 | 26 | $1,535.34 | 183 | $280,967 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 19 | $1,087.37 | 89 | $96,776 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 07 | 1 | $1,256.00 | +15.5% | 6 |
| 12 | 6 | $1,087.06 | -0% | 14 |
| 13 | 12 | $1,072.76 | -1.3% | 69 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0635 2 30 (Pull & Splice BOX, Install) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 19 contracts with a quantity-weighted average of $1,087.37 per EA, on 89 EA worth $96,776 in total.
The same report run for earlier periods shows $1,624.77 in 2024 (13 contracts, 113 EA), $1,535.34 in 2025 (26 contracts, 183 EA), $1,087.37 in the latest 12 months (19 contracts, 89 EA). From 2024 to the latest 12 months the weighted average fell 33.1%.
Quantity let statewide shrank 21% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 3 of FDOT's 14 market areas reported this item: area 07 at $1,256.00 (1 contract), area 12 at $1,087.06 (6 contracts), area 13 at $1,072.76 (12 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0635: 0635 2 11 Pull & Splice BOX, F&I, 13" X 24" Cover Size ($1,430.96 per EA, 168 contracts); 0635 2 12 Pull & Splice BOX, F&I, 24" X 36" Cover Size ($2,733.97 per EA, 77 contracts); 0635 2 14 Pull & Splice BOX, F&I, 17" X 30" Cover Size ($1,763.94 per EA, 40 contracts); 0635 2 13 Pull & Splice BOX, F&I, 30" X 60" Rectangular OR 36" Round Cover Size ($5,683.80 per EA, 39 contracts); 0635 3 13 Junction BOX, Furnish & Install, Embedded ($1,096.34 per EA, 23 contracts).
Related items in section 0635
- 0635 2 11 · Pull & Splice BOX, F&I, 13" X 24" Cover Size ($1,430.96/EA)
- 0635 2 12 · Pull & Splice BOX, F&I, 24" X 36" Cover Size ($2,733.97/EA)
- 0635 2 14 · Pull & Splice BOX, F&I, 17" X 30" Cover Size ($1,763.94/EA)
- 0635 2 13 · Pull & Splice BOX, F&I, 30" X 60" Rectangular OR 36" Round Cover Size ($5,683.80/EA)
- 0635 3 13 · Junction BOX, Furnish & Install, Embedded ($1,096.34/EA)
- 0635 3 12 · Junction BOX, Furnish & Install, Mounted ($851.16/EA)
- 0635 4 11 · Fiber Optic Splice Vault, Furnish & Install, 54"W X 54"L X 48"D ($12,556.27/EA)
- 0635 2 15 · Pull & Splice BOX, F&I, 30" X 48" Cover Size ($3,440.00/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.