Removal OF Existing Concrete (Item 0110 4 10): FDOT Unit Price History
194 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY
- Weighted average (12 mo)
- $34.86/SY
- Contracts (12 mo)
- 194
- Total quantity (12 mo)
- 428,444 SY
- Total amount (12 mo)
- $14,936,987
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 244 | $47.79 | 562,581 | $26,884,786 |
| 2025 | 2025-01-01 – 2025-12-31 | 223 | $37.87 | 487,211 | $18,452,352 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 194 | $34.86 | 428,444 | $14,936,987 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 12 | $18.60 | -46.6% | 31,664 |
| 02 | 9 | $91.07 | +161.2% | 1,651 |
| 03 | 10 | $53.23 | +52.7% | 15,176 |
| 04 | 10 | $54.09 | +55.2% | 4,021 |
| 05 | 19 | $27.46 | -21.2% | 87,839 |
| 06 | 14 | $30.51 | -12.5% | 14,427 |
| 07 | 17 | $39.09 | +12.1% | 18,134 |
| 08 | 43 | $31.31 | -10.2% | 88,509 |
| 09 | 3 | $35.18 | +0.9% | 3,285 |
| 10 | 13 | $41.71 | +19.7% | 17,764 |
| 11 | 5 | $26.69 | -23.4% | 15,227 |
| 12 | 23 | $40.90 | +17.3% | 93,831 |
| 13 | 15 | $46.57 | +33.6% | 36,518 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0110 4 10 (Removal OF Existing Concrete) is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 194 contracts with a quantity-weighted average of $34.86 per SY, on 428,444 SY worth $14,936,987 in total.
The same report run for earlier periods shows $47.79 in 2024 (244 contracts, 562,581 SY), $37.87 in 2025 (223 contracts, 487,211 SY), $34.86 in the latest 12 months (194 contracts, 428,444 SY). From 2024 to the latest 12 months the weighted average fell 27.1%.
Quantity let statewide shrank 24% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 01 had the lowest weighted average ($18.60 per SY, 12 contracts) and market area 02 the highest ($91.07, 9 contracts), 4.9 times as much. Market area 08 let the most contracts with this item (43). 13 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0110: 0110 1 1 Clearing & Grubbing ($52,554.01 per AC, 231 contracts); 0110 21 Tree Protection Barrier ($4.87 per LF, 47 contracts); 0110 3 Removal OF Existing Structures/Bridges ($58.97 per SF, 36 contracts); 0110 22 Tree Root AND Branch Pruning ($828.28 per EA, 30 contracts); 0110 7 1 Mailbox, F&I Single ($387.04 per EA, 26 contracts).
Related items in section 0110
- 0110 1 1 · Clearing & Grubbing ($52,554.01/AC)
- 0110 21 · Tree Protection Barrier ($4.87/LF)
- 0110 3 · Removal OF Existing Structures/Bridges ($58.97/SF)
- 0110 22 · Tree Root AND Branch Pruning ($828.28/EA)
- 0110 7 1 · Mailbox, F&I Single ($387.04/EA)
- 0110 2 2 · Selective Clearing AND Grubbing, Areas With Trees TO Remain ($14,713.50/AC)
- 0110 23 · Tree Removal ($303.42/EA)
- 0110 71 1 · Bridge Fender System, Removal & Disposal ($1,484.88/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.