Removal OF Existing Concrete (Item 0110 4 10): FDOT Unit Price History

194 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY

Weighted average (12 mo)
$34.86/SY
Contracts (12 mo)
194
Total quantity (12 mo)
428,444 SY
Total amount (12 mo)
$14,936,987

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31244$47.79562,581$26,884,786
20252025-01-01 – 2025-12-31223$37.87487,211$18,452,352
Latest 12 months2025-11-01 – 2026-10-31194$34.86428,444$14,936,987

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
0112$18.60-46.6%31,664
029$91.07+161.2%1,651
0310$53.23+52.7%15,176
0410$54.09+55.2%4,021
0519$27.46-21.2%87,839
0614$30.51-12.5%14,427
0717$39.09+12.1%18,134
0843$31.31-10.2%88,509
093$35.18+0.9%3,285
1013$41.71+19.7%17,764
115$26.69-23.4%15,227
1223$40.90+17.3%93,831
1315$46.57+33.6%36,518

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0110 4 10 (Removal OF Existing Concrete) is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 194 contracts with a quantity-weighted average of $34.86 per SY, on 428,444 SY worth $14,936,987 in total.

The same report run for earlier periods shows $47.79 in 2024 (244 contracts, 562,581 SY), $37.87 in 2025 (223 contracts, 487,211 SY), $34.86 in the latest 12 months (194 contracts, 428,444 SY). From 2024 to the latest 12 months the weighted average fell 27.1%.

Quantity let statewide shrank 24% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 01 had the lowest weighted average ($18.60 per SY, 12 contracts) and market area 02 the highest ($91.07, 9 contracts), 4.9 times as much. Market area 08 let the most contracts with this item (43). 13 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0110: 0110 1 1 Clearing & Grubbing ($52,554.01 per AC, 231 contracts); 0110 21 Tree Protection Barrier ($4.87 per LF, 47 contracts); 0110 3 Removal OF Existing Structures/Bridges ($58.97 per SF, 36 contracts); 0110 22 Tree Root AND Branch Pruning ($828.28 per EA, 30 contracts); 0110 7 1 Mailbox, F&I Single ($387.04 per EA, 26 contracts).

Related items in section 0110

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.