Clearing & Grubbing (Item 0110 1 1): FDOT Unit Price History

231 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AC

Weighted average (12 mo)
$52,554.01/AC
Contracts (12 mo)
231
Total quantity (12 mo)
2,159.35 AC
Total amount (12 mo)
$113,482,509

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31275$53,172.932,345.93$124,739,966
20252025-01-01 – 2025-12-31261$47,528.633,053.9$145,147,488
Latest 12 months2025-11-01 – 2026-10-31231$52,554.012,159.35$113,482,509

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
0116$22,003.84-58.1%111.22
0213$23,692.96-54.9%22.34
0315$14,993.56-71.5%109.09
0415$16,929.74-67.8%91.69
0521$67,029.34+27.5%33.6
0617$12,026.33-77.1%131.44
0720$38,918.07-25.9%895.98
0849$36,119.42-31.3%187.61
096$45,298.74-13.8%17.75
1013$58,113.70+10.6%31.96
115$281,365.92+435.4%39.83
1223$90,080.64+71.4%459.41
1315$241,840.24+360.2%26.13
141$96,153.85+83%1.04

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0110 1 1 (Clearing & Grubbing) is measured in AC. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 231 contracts with a quantity-weighted average of $52,554.01 per AC, on 2,159.35 AC worth $113,482,509 in total.

The same report run for earlier periods shows $53,172.93 in 2024 (275 contracts, 2,345.93 AC), $47,528.63 in 2025 (261 contracts, 3,053.9 AC), $52,554.01 in the latest 12 months (231 contracts, 2,159.35 AC). Across those periods the weighted average stayed within three percent.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 06 had the lowest weighted average ($12,026.33 per AC, 17 contracts) and market area 11 the highest ($281,365.92, 5 contracts), 23.4 times as much. Market area 08 let the most contracts with this item (49). 14 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0110: 0110 4 10 Removal OF Existing Concrete ($34.86 per SY, 194 contracts); 0110 21 Tree Protection Barrier ($4.87 per LF, 47 contracts); 0110 3 Removal OF Existing Structures/Bridges ($58.97 per SF, 36 contracts); 0110 22 Tree Root AND Branch Pruning ($828.28 per EA, 30 contracts); 0110 7 1 Mailbox, F&I Single ($387.04 per EA, 26 contracts).

Related items in section 0110

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.