Removal OF Existing Structures/Bridges (Item 0110 3): FDOT Unit Price History
36 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SF
- Weighted average (12 mo)
- $58.97/SF
- Contracts (12 mo)
- 36
- Total quantity (12 mo)
- 464,502 SF
- Total amount (12 mo)
- $27,392,496
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 26 | $87.31 | 358,885 | $31,333,236 |
| 2025 | 2025-01-01 – 2025-12-31 | 31 | $121.77 | 374,441 | $45,595,777 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 36 | $58.97 | 464,502 | $27,392,496 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 6 | $40.45 | -31.4% | 20,489 |
| 02 | 5 | $29.11 | -50.6% | 21,748 |
| 03 | 3 | $50.58 | -14.2% | 20,582 |
| 04 | 4 | $26.79 | -54.6% | 22,371 |
| 05 | 2 | $20.28 | -65.6% | 26,696 |
| 07 | 2 | $35.97 | -39% | 41,507 |
| 08 | 1 | $272.33 | +361.8% | 918 |
| 10 | 1 | $51.49 | -12.7% | 97,904 |
| 11 | 2 | $77.93 | +32.2% | 55,070 |
| 12 | 6 | $70.74 | +20% | 149,163 |
| 13 | 3 | $399.00 | +576.6% | 4,604 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0110 3 (Removal OF Existing Structures/Bridges) is measured in SF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 36 contracts with a quantity-weighted average of $58.97 per SF, on 464,502 SF worth $27,392,496 in total.
The same report run for earlier periods shows $87.31 in 2024 (26 contracts, 358,885 SF), $121.77 in 2025 (31 contracts, 374,441 SF), $58.97 in the latest 12 months (36 contracts, 464,502 SF). From 2024 to the latest 12 months the weighted average fell 32.5%.
Quantity let statewide grew 29% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 6 market areas with at least three contracts, market area 04 had the lowest weighted average ($26.79 per SF, 4 contracts) and market area 13 the highest ($399.00, 3 contracts), 14.9 times as much. Market area 01 let the most contracts with this item (6). 11 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0110: 0110 1 1 Clearing & Grubbing ($52,554.01 per AC, 231 contracts); 0110 4 10 Removal OF Existing Concrete ($34.86 per SY, 194 contracts); 0110 21 Tree Protection Barrier ($4.87 per LF, 47 contracts); 0110 22 Tree Root AND Branch Pruning ($828.28 per EA, 30 contracts); 0110 7 1 Mailbox, F&I Single ($387.04 per EA, 26 contracts).
Related items in section 0110
- 0110 1 1 · Clearing & Grubbing ($52,554.01/AC)
- 0110 4 10 · Removal OF Existing Concrete ($34.86/SY)
- 0110 21 · Tree Protection Barrier ($4.87/LF)
- 0110 22 · Tree Root AND Branch Pruning ($828.28/EA)
- 0110 7 1 · Mailbox, F&I Single ($387.04/EA)
- 0110 2 2 · Selective Clearing AND Grubbing, Areas With Trees TO Remain ($14,713.50/AC)
- 0110 23 · Tree Removal ($303.42/EA)
- 0110 71 1 · Bridge Fender System, Removal & Disposal ($1,484.88/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.