Temporary Separator, F&I Remove (Item 0102 75 1): FDOT Unit Price History

19 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$16.29/LF
Contracts (12 mo)
19
Total quantity (12 mo)
82,220 LF
Total amount (12 mo)
$1,339,723

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3117$31.4649,820$1,567,312
20252025-01-01 – 2025-12-3115$18.8279,202$1,490,697
Latest 12 months2025-11-01 – 2026-10-3119$16.2982,220$1,339,723

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$19.00+16.6%27,165
041$22.00+35.1%900
051$14.00-14.1%2,127
061$11.00-32.5%400
073$17.16+5.3%7,033
084$13.87-14.9%8,024
091$24.50+50.4%3,831
102$19.42+19.2%3,549
111$21.00+28.9%700
122$8.36-48.7%17,436
132$19.38+19%11,055

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0102 75 1 (Temporary Separator, F&I Remove) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 19 contracts with a quantity-weighted average of $16.29 per LF, on 82,220 LF worth $1,339,723 in total.

The same report run for earlier periods shows $31.46 in 2024 (17 contracts, 49,820 LF), $18.82 in 2025 (15 contracts, 79,202 LF), $16.29 in the latest 12 months (19 contracts, 82,220 LF). From 2024 to the latest 12 months the weighted average fell 48.2%.

Quantity let statewide grew 65% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 11 of FDOT's 14 market areas reported this item: area 01 at $19.00 (1 contract), area 04 at $22.00 (1 contract), area 05 at $14.00 (1 contract), area 06 at $11.00 (1 contract), area 07 at $17.16 (3 contracts), area 08 at $13.87 (4 contracts), area 09 at $24.50 (1 contract), area 10 at $19.42 (2 contracts), area 11 at $21.00 (1 contract), area 12 at $8.36 (2 contracts), area 13 at $19.38 (2 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).

Related items in section 0102

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.