Temporary Separator, F&I Remove (Item 0102 75 1): FDOT Unit Price History
19 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $16.29/LF
- Contracts (12 mo)
- 19
- Total quantity (12 mo)
- 82,220 LF
- Total amount (12 mo)
- $1,339,723
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 17 | $31.46 | 49,820 | $1,567,312 |
| 2025 | 2025-01-01 – 2025-12-31 | 15 | $18.82 | 79,202 | $1,490,697 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 19 | $16.29 | 82,220 | $1,339,723 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $19.00 | +16.6% | 27,165 |
| 04 | 1 | $22.00 | +35.1% | 900 |
| 05 | 1 | $14.00 | -14.1% | 2,127 |
| 06 | 1 | $11.00 | -32.5% | 400 |
| 07 | 3 | $17.16 | +5.3% | 7,033 |
| 08 | 4 | $13.87 | -14.9% | 8,024 |
| 09 | 1 | $24.50 | +50.4% | 3,831 |
| 10 | 2 | $19.42 | +19.2% | 3,549 |
| 11 | 1 | $21.00 | +28.9% | 700 |
| 12 | 2 | $8.36 | -48.7% | 17,436 |
| 13 | 2 | $19.38 | +19% | 11,055 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0102 75 1 (Temporary Separator, F&I Remove) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 19 contracts with a quantity-weighted average of $16.29 per LF, on 82,220 LF worth $1,339,723 in total.
The same report run for earlier periods shows $31.46 in 2024 (17 contracts, 49,820 LF), $18.82 in 2025 (15 contracts, 79,202 LF), $16.29 in the latest 12 months (19 contracts, 82,220 LF). From 2024 to the latest 12 months the weighted average fell 48.2%.
Quantity let statewide grew 65% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 11 of FDOT's 14 market areas reported this item: area 01 at $19.00 (1 contract), area 04 at $22.00 (1 contract), area 05 at $14.00 (1 contract), area 06 at $11.00 (1 contract), area 07 at $17.16 (3 contracts), area 08 at $13.87 (4 contracts), area 09 at $24.50 (1 contract), area 10 at $19.42 (2 contracts), area 11 at $21.00 (1 contract), area 12 at $8.36 (2 contracts), area 13 at $19.38 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).
Related items in section 0102
- 0102 1 · Maintenance OF Traffic ($1,069.75/DA)
- 0102 60 · Work Zone Sign ($0.230/ED)
- 0102 74 1 · Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110/ED)
- 0102 99 · Portable Changeable Message Sign, Temporary ($10.81/ED)
- 0102 76 · Arrow Board / Advance Warning Arrow Panel ($5.10/ED)
- 0102 14 · Traffic Control Officer ($53.78/HR)
- 0102 74 8 · Channelizing Device- Pedestrian LCD (Longitudinal Channelizing Device) ($0.060/FD)
- 0102 4 1 · Pedestrian OR Bicycle Special Detour ($55.15/SY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.