Channelizing Device- Pedestrian LCD (Longitudinal Channelizing Device) (Item 0102 74 8): FDOT Unit Price History

165 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure FD

Weighted average (12 mo)
$0.060/FD
Contracts (12 mo)
165
Total quantity (12 mo)
13,100,232 FD
Total amount (12 mo)
$751,608

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31209$0.05026,836,901$1,390,783
20252025-01-01 – 2025-12-31195$0.06032,023,281$2,055,760
Latest 12 months2025-11-01 – 2026-10-31165$0.06013,100,232$751,608

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
015$0.050-16.7%2,200,389
025$0.650+983.3%2,957
0311$0.090+50%886,949
043$0.080+33.3%17,608
0517$0.0600%976,118
0613$0.090+50%151,269
0714$0.050-16.7%2,036,020
0841$0.050-16.7%2,172,284
093$0.050-16.7%33,951
1011$0.050-16.7%1,691,278
116$0.070+16.7%1,888,326
1219$0.040-33.3%483,445
1314$0.050-16.7%408,085
141$0.090+50%12,880

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0102 74 8 (Channelizing Device- Pedestrian LCD (Longitudinal Channelizing Device)) is measured in FD. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 165 contracts with a quantity-weighted average of $0.060 per FD, on 13,100,232 FD worth $751,608 in total.

The same report run for earlier periods shows $0.050 in 2024 (209 contracts, 26,836,901 FD), $0.060 in 2025 (195 contracts, 32,023,281 FD), $0.060 in the latest 12 months (165 contracts, 13,100,232 FD). From 2024 to the latest 12 months the weighted average rose 20.0%.

Quantity let statewide shrank 51% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 13 market areas with at least three contracts, market area 12 had the lowest weighted average ($0.040 per FD, 19 contracts) and market area 02 the highest ($0.650, 5 contracts), 16.3 times as much. Market area 08 let the most contracts with this item (41). 14 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).

Related items in section 0102

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.