Temporary Barrier, Relocate, Free Standing (Item 0102 71 26): FDOT Unit Price History
14 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $7.67/LF
- Contracts (12 mo)
- 14
- Total quantity (12 mo)
- 212,523 LF
- Total amount (12 mo)
- $1,629,476
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 22 | $4.53 | 241,489 | $1,094,875 |
| 2025 | 2025-01-01 – 2025-12-31 | 26 | $6.54 | 271,612 | $1,775,569 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 14 | $7.67 | 212,523 | $1,629,476 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 04 | 1 | $12.40 | +61.7% | 2,066 |
| 05 | 1 | $1.00 | -87% | 22,497 |
| 07 | 4 | $10.53 | +37.3% | 112,200 |
| 08 | 1 | $8.00 | +4.3% | 353 |
| 09 | 1 | $0.010 | -99.9% | 525 |
| 10 | 2 | $7.75 | +1% | 4,050 |
| 11 | 1 | $8.50 | +10.8% | 2,032 |
| 12 | 3 | $5.06 | -34% | 68,800 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0102 71 26 (Temporary Barrier, Relocate, Free Standing) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 14 contracts with a quantity-weighted average of $7.67 per LF, on 212,523 LF worth $1,629,476 in total.
The same report run for earlier periods shows $4.53 in 2024 (22 contracts, 241,489 LF), $6.54 in 2025 (26 contracts, 271,612 LF), $7.67 in the latest 12 months (14 contracts, 212,523 LF). From 2024 to the latest 12 months the weighted average rose 69.3%.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 04 at $12.40 (1 contract), area 05 at $1.00 (1 contract), area 07 at $10.53 (4 contracts), area 08 at $8.00 (1 contract), area 09 at $0.010 (1 contract), area 10 at $7.75 (2 contracts), area 11 at $8.50 (1 contract), area 12 at $5.06 (3 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).
Related items in section 0102
- 0102 1 · Maintenance OF Traffic ($1,069.75/DA)
- 0102 60 · Work Zone Sign ($0.230/ED)
- 0102 74 1 · Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110/ED)
- 0102 99 · Portable Changeable Message Sign, Temporary ($10.81/ED)
- 0102 76 · Arrow Board / Advance Warning Arrow Panel ($5.10/ED)
- 0102 14 · Traffic Control Officer ($53.78/HR)
- 0102 74 8 · Channelizing Device- Pedestrian LCD (Longitudinal Channelizing Device) ($0.060/FD)
- 0102 4 1 · Pedestrian OR Bicycle Special Detour ($55.15/SY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.