Temporary Barrier, Relocate, Anchored (Item 0102 71 25): FDOT Unit Price History

34 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$8.62/LF
Contracts (12 mo)
34
Total quantity (12 mo)
272,765 LF
Total amount (12 mo)
$2,350,172

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3124$10.12365,623$3,700,022
20252025-01-01 – 2025-12-3132$7.06465,997$3,288,517
Latest 12 months2025-11-01 – 2026-10-3134$8.62272,765$2,350,172

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$32.13+272.7%2,445
021$25.00+190%200
033$13.57+57.4%3,426
046$13.26+53.8%13,239
051$17.50+103%300
076$20.17+134%50,270
086$15.51+79.9%7,625
091$1.00-88.4%2,538
103$17.80+106.5%2,604
111$16.20+87.9%6,384
125$4.11-52.3%183,734

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0102 71 25 (Temporary Barrier, Relocate, Anchored) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 34 contracts with a quantity-weighted average of $8.62 per LF, on 272,765 LF worth $2,350,172 in total.

The same report run for earlier periods shows $10.12 in 2024 (24 contracts, 365,623 LF), $7.06 in 2025 (32 contracts, 465,997 LF), $8.62 in the latest 12 months (34 contracts, 272,765 LF). From 2024 to the latest 12 months the weighted average fell 14.8%.

Quantity let statewide shrank 25% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 6 market areas with at least three contracts, market area 12 had the lowest weighted average ($4.11 per LF, 5 contracts) and market area 07 the highest ($20.17, 6 contracts), 4.9 times as much. Market area 04 let the most contracts with this item (6). 11 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).

Related items in section 0102

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.