Temporary Barrier, F&I, LOW Profile, Concrete (Item 0102 71 13): FDOT Unit Price History

65 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$32.06/LF
Contracts (12 mo)
65
Total quantity (12 mo)
143,918 LF
Total amount (12 mo)
$4,614,530

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3181$29.21183,684$5,364,971
20252025-01-01 – 2025-12-3182$39.59160,842$6,368,119
Latest 12 months2025-11-01 – 2026-10-3165$32.06143,918$4,614,530

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
014$51.11+59.4%11,938
022$52.64+64.2%528
035$52.77+64.6%4,513
041$44.00+37.2%406
056$32.73+2.1%9,534
063$42.85+33.7%5,496
078$42.89+33.8%17,131
0813$38.52+20.1%18,791
106$38.79+21%33,972
113$2.43-92.4%5,917
129$13.61-57.5%23,658
133$0.010-100%9,494
141$0.010-100%1,340

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0102 71 13 (Temporary Barrier, F&I, LOW Profile, Concrete) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 65 contracts with a quantity-weighted average of $32.06 per LF, on 143,918 LF worth $4,614,530 in total.

The same report run for earlier periods shows $29.21 in 2024 (81 contracts, 183,684 LF), $39.59 in 2025 (82 contracts, 160,842 LF), $32.06 in the latest 12 months (65 contracts, 143,918 LF). From 2024 to the latest 12 months the weighted average rose 9.8%.

Quantity let statewide shrank 22% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 10 market areas with at least three contracts, market area 13 had the lowest weighted average ($0.010 per LF, 3 contracts) and market area 03 the highest ($52.77, 5 contracts), 5277.0 times as much. Market area 08 let the most contracts with this item (13). 13 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).

Related items in section 0102

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.