Barrier Mounted Work Zone Sign- Index 700-013 (Item 0102 62 13): FDOT Unit Price History
15 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure ED
- Weighted average (12 mo)
- $0.540/ED
- Contracts (12 mo)
- 15
- Total quantity (12 mo)
- 54,222 ED
- Total amount (12 mo)
- $29,057
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 14 | $0.590 | 112,974 | $67,115 |
| 2025 | 2025-01-01 – 2025-12-31 | 16 | $0.490 | 144,810 | $70,649 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 15 | $0.540 | 54,222 | $29,057 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 02 | 1 | $0.340 | -37% | 882 |
| 03 | 1 | $5.53 | +924.1% | 180 |
| 04 | 1 | $0.400 | -25.9% | 1,813 |
| 05 | 5 | $0.480 | -11.1% | 7,428 |
| 07 | 2 | $0.570 | +5.6% | 5,708 |
| 08 | 2 | $1.44 | +166.7% | 5,005 |
| 11 | 1 | $0.540 | 0% | 1,167 |
| 12 | 2 | $0.390 | -27.8% | 32,039 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0102 62 13 (Barrier Mounted Work Zone Sign- Index 700-013) is measured in ED. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 15 contracts with a quantity-weighted average of $0.540 per ED, on 54,222 ED worth $29,057 in total.
The same report run for earlier periods shows $0.590 in 2024 (14 contracts, 112,974 ED), $0.490 in 2025 (16 contracts, 144,810 ED), $0.540 in the latest 12 months (15 contracts, 54,222 ED). From 2024 to the latest 12 months the weighted average fell 8.5%.
Quantity let statewide shrank 52% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 02 at $0.340 (1 contract), area 03 at $5.53 (1 contract), area 04 at $0.400 (1 contract), area 05 at $0.480 (5 contracts), area 07 at $0.570 (2 contracts), area 08 at $1.44 (2 contracts), area 11 at $0.540 (1 contract), area 12 at $0.390 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).
Related items in section 0102
- 0102 1 · Maintenance OF Traffic ($1,069.75/DA)
- 0102 60 · Work Zone Sign ($0.230/ED)
- 0102 74 1 · Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110/ED)
- 0102 99 · Portable Changeable Message Sign, Temporary ($10.81/ED)
- 0102 76 · Arrow Board / Advance Warning Arrow Panel ($5.10/ED)
- 0102 14 · Traffic Control Officer ($53.78/HR)
- 0102 74 8 · Channelizing Device- Pedestrian LCD (Longitudinal Channelizing Device) ($0.060/FD)
- 0102 4 1 · Pedestrian OR Bicycle Special Detour ($55.15/SY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.