Temporary Highway Lighting (Item 0102 30): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $695.80/EA
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 3,970 EA
- Total amount (12 mo)
- $2,762,323
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 11 | $1,466.34 | 4,151 | $6,086,789 |
| 2025 | 2025-01-01 – 2025-12-31 | 14 | $2,039.26 | 3,180 | $6,484,860 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $695.80 | 3,970 | $2,762,323 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 07 | 1 | $9,979.59 | +1,334.3% | 49 |
| 08 | 5 | $4,167.72 | +499% | 90 |
| 12 | 4 | $505.92 | -27.3% | 3,752 |
| 13 | 2 | $0.030 | -100% | 79 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0102 30 (Temporary Highway Lighting) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $695.80 per EA, on 3,970 EA worth $2,762,323 in total.
The same report run for earlier periods shows $1,466.34 in 2024 (11 contracts, 4,151 EA), $2,039.26 in 2025 (14 contracts, 3,180 EA), $695.80 in the latest 12 months (12 contracts, 3,970 EA). From 2024 to the latest 12 months the weighted average fell 52.5%.
In the same 12 months, 4 of FDOT's 14 market areas reported this item: area 07 at $9,979.59 (1 contract), area 08 at $4,167.72 (5 contracts), area 12 at $505.92 (4 contracts), area 13 at $0.030 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0102: 0102 1 Maintenance OF Traffic ($1,069.75 per DA, 266 contracts); 0102 60 Work Zone Sign ($0.230 per ED, 265 contracts); 0102 74 1 Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110 per ED, 263 contracts); 0102 99 Portable Changeable Message Sign, Temporary ($10.81 per ED, 257 contracts); 0102 76 Arrow Board / Advance Warning Arrow Panel ($5.10 per ED, 208 contracts).
Related items in section 0102
- 0102 1 · Maintenance OF Traffic ($1,069.75/DA)
- 0102 60 · Work Zone Sign ($0.230/ED)
- 0102 74 1 · Channelizing Device- Types I, II, DI, VP, Drum, OR LCD ($0.110/ED)
- 0102 99 · Portable Changeable Message Sign, Temporary ($10.81/ED)
- 0102 76 · Arrow Board / Advance Warning Arrow Panel ($5.10/ED)
- 0102 14 · Traffic Control Officer ($53.78/HR)
- 0102 74 8 · Channelizing Device- Pedestrian LCD (Longitudinal Channelizing Device) ($0.060/FD)
- 0102 4 1 · Pedestrian OR Bicycle Special Detour ($55.15/SY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.