Reyes TX, Inc.: TxDOT Bid Results and Margins

Name as published by TxDOT: REYES TX, INC. · Data as published by TxDOT, lettings Jun 2, 2026 to Oct 6, 2026, retrieved Nov 24, 2026.

Proposals bid
5
Low bids (rank 1)
1
Win rate
20%
Low-bid value
$19.8M
Money left on table
$327K
Avg. bid vs. estimate
-19.28%

From Jun 2, 2026 to Oct 6, 2026, Reyes TX, Inc. submitted 5 bids on TxDOT proposals and was the apparent low bidder on 1 of them (20%), with low bids totalling $19,812,334. In 1 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $326,998 (1.65% of those bids); the median gap was 1.65%. On average its bids came in 19.28% below TxDOT's engineer's estimate. Its most frequent district was Fort Worth (4 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20265120.0%$19,812,334

Head-to-head rivals

BidderProposals togetherRanked ahead
Ragle Construction, Inc.41 of 4
Indus Road & Bridge, Inc.30 of 3
Austin Bridge & Road Services, LP21 of 2
Ed Bell Construction Company22 of 2
Harper Brothers Construction LLC20 of 2
James Construction Group, LLC21 of 2
Jay Mills Contracting, Incorporated22 of 2
Mario Sinacola & Sons Excavating, Inc.22 of 2

Districts and work types

DistrictBids
Fort Worth4
Dallas1
Work type of low bidsLow bids
Widen Non-Freeway1

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-10-060009-11-248DallasInterchange (New or Reconstructed)4 of 7$59,000,000+8.5%-91.3%
2026-08-060314-07-070ParkerRehabilitation of Existing Road3 of 7$16,000,000+1.9%-11.9%
2026-08-050014-15-034TarrantIntersection & Operational Imprv5 of 11$70,600,000+6.7%-5%
2026-07-010014-03-088JohnsonInterchange (New or Reconstructed)6 of 6$80,500,000+25%+13%
2026-06-020019-01-146JohnsonWiden Non-Freeway1 of 8$19,812,334—-1.2%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.