Project Allied Resources, LLC: TxDOT Bid Results and Margins
Name as published by TxDOT: PROJECT ALLIED RESOURCES, LLC · Data as published by TxDOT, lettings Nov 6, 2024 to Jun 3, 2026, retrieved Nov 24, 2026.
- Proposals bid
- 6
- Low bids (rank 1)
- 0
- Win rate
- 0%
- Low-bid value
- $0.000
- Money left on table
- —
- Avg. bid vs. estimate
- +8.37%
From Nov 6, 2024 to Jun 3, 2026, Project Allied Resources, LLC submitted 6 bids on TxDOT proposals and was the apparent low bidder on 0 of them (0%), with low bids totalling $0. On average its bids came in 8.37% above TxDOT's engineer's estimate. Its most frequent district was Brownwood (2 bids).
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
By year
| Year | Bids | Low bids | Win rate | Low-bid value |
|---|---|---|---|---|
| 2024 | 2 | 0 | 0.0% | $0 |
| 2025 | 3 | 0 | 0.0% | $0 |
| 2026 | 1 | 0 | 0.0% | $0 |
Head-to-head rivals
| Bidder | Proposals together | Ranked ahead |
|---|---|---|
| Skyline Bridge LLC | 3 | 2 of 3 |
| Stx Civil | 3 | 1 of 3 |
| Thk Construction LLC | 3 | 1 of 3 |
| A. L. Helmcamp, Inc. | 2 | 1 of 2 |
| C. E. Barker, Ltd. | 2 | 2 of 2 |
| Delgado's Contractors, LLC | 2 | 0 of 2 |
| Hodges and Son Construction Company, Inc. | 2 | 1 of 2 |
| Lakey, Inc. | 2 | 1 of 2 |
Districts and work types
| District | Bids |
|---|---|
| Brownwood | 2 |
| Beaumont | 1 |
| Fort Worth | 1 |
| Paris | 1 |
| Wichita Falls | 1 |
Closest second-place finishes
| Let date | Proposal | County | Low bidder | Low bid | This bid | vs. low bid |
|---|---|---|---|---|---|---|
| 2025-02-06 | 0137-05-035 | Archer | Altus Construction LLC | $6,506,472 | $6,619,747 | +1.7% |
Recent bids
| Let date | Proposal | County | Work type | Rank | Bid total | vs. low bid | vs. estimate |
|---|---|---|---|---|---|---|---|
| 2026-06-03 | 0923-08-042 | Coleman | Pedestrian, Sidewalks & Curb Ramps | 4 of 4 | $3,040,500 | +38.8% | +19.5% |
| 2025-03-04 | 0902-49-076 | Erath | Bridge Replacement | 5 of 8 | $1,529,611 | +7.6% | -1.9% |
| 2025-02-06 | 0137-05-035 | Archer | Bridge Replacement | 2 of 7 | $6,619,747 | +1.7% | -3.5% |
| 2025-01-08 | 0920-12-049 | Jasper | Bridge Replacement | 8 of 8 | $2,275,338 | +14.9% | +22.1% |
| 2024-12-03 | 0923-23-032 | Mills | Bridge Replacement | 8 of 9 | $2,066,790 | +40.6% | +21% |
| 2024-11-06 | 0221-01-083 | Lamar | Pedestrian, Sidewalks & Curb Ramps | 3 of 9 | $2,357,714 | +6.1% | -7% |
Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.
Compare your own unit prices with TxDOT history: benchmark a bid tab.