Forde Construction Company, Inc.: TxDOT Bid Results and Margins
Name as published by TxDOT: FORDE CONSTRUCTION COMPANY, INC. · Data as published by TxDOT, lettings Nov 6, 2024 to Oct 6, 2026, retrieved Nov 24, 2026.
Proposals bid
66
Low bids (rank 1)
8
Win rate
12.12%
Low-bid value
$9.4M
Money left on table
$1.1M
Avg. bid vs. estimate
+11.69%
From Nov 6, 2024 to Oct 6, 2026, Forde Construction Company, Inc. submitted 66 bids on TxDOT proposals and was the apparent low bidder on 8 of them (12.12%), with low bids totalling $9,422,856. In 8 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $1,091,526 (11.58% of those bids); the median gap was 2.22%. On average its bids came in 11.69% above TxDOT's engineer's estimate. Its most frequent district was Houston (41 bids).
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.