Name as published by TxDOT: A-1 DOT SOLUTIONS LLC · Data as published by TxDOT, lettings Nov 20, 2024 to Sep 17, 2025, retrieved Nov 24, 2026.

Proposals bid
5
Low bids (rank 1)
1
Win rate
20%
Low-bid value
$141K
Money left on table
$19K
Avg. bid vs. estimate
+3.87%

From Nov 20, 2024 to Sep 17, 2025, A-1 Dot Solutions LLC submitted 5 bids on TxDOT proposals and was the apparent low bidder on 1 of them (20%), with low bids totalling $141,123. In 1 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $18,682 (13.24% of those bids); the median gap was 13.24%. On average its bids came in 3.87% above TxDOT's engineer's estimate. Its most frequent district was San Antonio (2 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
2024200.0%$0
20253133.3%$141,123

Head-to-head rivals

BidderProposals togetherRanked ahead
Anahuac Infrastructure LLC21 of 2
A. L. Helmcamp, Inc.10 of 1
Aad Contracting Inc.10 of 1
Above All Contracting LLC10 of 1
Albeco Contractors LLC10 of 1
American Infrastructure Maintenance Management LLC11 of 1
Bk Field Operations LLC10 of 1
Bootstraps Occupational Services Incorporated11 of 1

Districts and work types

DistrictBids
San Antonio2
Atlanta1
Pharr1
Tyler1
Work type of low bidsLow bids
Bridge Widening or Rehabilitation1

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2025-09-176489-91-001KerrRoutine Maintenance Project4 of 9$652,304+24.4%-18.3%
2025-01-216478-11-001AndersonRoutine Maintenance Project6 of 6$777,750+78.2%+51.3%
2025-01-080915-12-690BexarBridge Widening or Rehabilitation1 of 4$141,123—-21%
2024-12-030621-01-118HidalgoBridge Maintenance7 of 7$74,918+291.2%+42.2%
2024-11-206472-05-001TitusRoutine Maintenance Project4 of 5$269,870+44.7%-34.8%