Painted Pavement Markings, Standard, White, Solid FOR Diagonal OR Chevron, 18" (Item 0710 11124): FDOT Unit Price History

98 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$2.01/LF
Contracts (12 mo)
98
Total quantity (12 mo)
104,297 LF
Total amount (12 mo)
$209,270

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31138$1.99154,014$307,108
20252025-01-01 – 2025-12-31129$2.47150,611$372,138
Latest 12 months2025-11-01 – 2026-10-3198$2.01104,297$209,270

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
014$1.78-11.4%1,770
026$1.01-49.8%3,359
036$3.08+53.2%2,515
048$2.08+3.5%7,808
0513$2.16+7.5%16,399
067$1.93-4%4,527
079$2.33+15.9%22,194
0821$1.73-13.9%23,013
093$1.63-18.9%3,877
1012$1.92-4.5%10,621
112$2.09+4%4,687
124$1.71-14.9%3,300
133$3.17+57.7%227

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0710 11124 (Painted Pavement Markings, Standard, White, Solid FOR Diagonal OR Chevron, 18") is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 98 contracts with a quantity-weighted average of $2.01 per LF, on 104,297 LF worth $209,270 in total.

The same report run for earlier periods shows $1.99 in 2024 (138 contracts, 154,014 LF), $2.47 in 2025 (129 contracts, 150,611 LF), $2.01 in the latest 12 months (98 contracts, 104,297 LF). Across those periods the weighted average stayed within three percent.

Quantity let statewide shrank 32% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 12 market areas with at least three contracts, market area 02 had the lowest weighted average ($1.01 per LF, 6 contracts) and market area 13 the highest ($3.17, 3 contracts), 3.1 times as much. Market area 08 let the most contracts with this item (21). 13 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0710: 0710 90 Painted Pavement Markings, Final Surface ($37,166.90 per LS, 223 contracts); 0710 11101 Painted Pavement Markings, Standard, White, Solid, 6" ($1,691.86 per GM, 177 contracts); 0710 11201 Painted Pavement Markings, Standard, Yellow, Solid, 6" ($1,745.98 per GM, 176 contracts); 0710 11125 Painted Pavement Markings, Standard, White, Solid FOR Stop Line OR Crosswalk, 24" ($2.24 per LF, 141 contracts); 0710 11170 Painted Pavement Markings, Standard, White, Arrows ($44.32 per EA, 131 contracts).

Related items in section 0710

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.