Painted Pavement Markings, Standard, White, Solid FOR Interchange Markings, 12" (Item 0710 11103): FDOT Unit Price History

12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure GM

Weighted average (12 mo)
$3,531.63/GM
Contracts (12 mo)
12
Total quantity (12 mo)
3.53 GM
Total amount (12 mo)
$12,456

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3122$4,309.5019.84$85,505
20252025-01-01 – 2025-12-3117$4,260.544.61$19,624
Latest 12 months2025-11-01 – 2026-10-3112$3,531.633.53$12,456

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
053$2,934.55-16.9%0.21
061$3,321.11-6%0.04
071$2,087.12-40.9%0.07
084$3,611.41+2.3%2.96
101$1,814.91-48.6%0.06
111$2,322.58-34.2%0.03
121$4,421.16+25.2%0.16

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0710 11103 (Painted Pavement Markings, Standard, White, Solid FOR Interchange Markings, 12") is measured in GM. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $3,531.63 per GM, on 3.53 GM worth $12,456 in total.

The same report run for earlier periods shows $4,309.50 in 2024 (22 contracts, 19.84 GM), $4,260.54 in 2025 (17 contracts, 4.61 GM), $3,531.63 in the latest 12 months (12 contracts, 3.53 GM). From 2024 to the latest 12 months the weighted average fell 18.1%.

Quantity let statewide shrank 82% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 05 at $2,934.55 (3 contracts), area 06 at $3,321.11 (1 contract), area 07 at $2,087.12 (1 contract), area 08 at $3,611.41 (4 contracts), area 10 at $1,814.91 (1 contract), area 11 at $2,322.58 (1 contract), area 12 at $4,421.16 (1 contract).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0710: 0710 90 Painted Pavement Markings, Final Surface ($37,166.90 per LS, 223 contracts); 0710 11101 Painted Pavement Markings, Standard, White, Solid, 6" ($1,691.86 per GM, 177 contracts); 0710 11201 Painted Pavement Markings, Standard, Yellow, Solid, 6" ($1,745.98 per GM, 176 contracts); 0710 11125 Painted Pavement Markings, Standard, White, Solid FOR Stop Line OR Crosswalk, 24" ($2.24 per LF, 141 contracts); 0710 11170 Painted Pavement Markings, Standard, White, Arrows ($44.32 per EA, 131 contracts).

Related items in section 0710

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.