Prestressed Concrete Pole, Complete Pole Removal- Pole 30' AND Greater (Item 0641 2 80): FDOT Unit Price History
21 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $11,463.97/EA
- Contracts (12 mo)
- 21
- Total quantity (12 mo)
- 93 EA
- Total amount (12 mo)
- $1,066,150
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 28 | $8,576.49 | 121 | $1,037,755 |
| 2025 | 2025-01-01 – 2025-12-31 | 25 | $9,740.48 | 139 | $1,353,926 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 21 | $11,463.97 | 93 | $1,066,150 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $7,334.00 | -36% | 2 |
| 05 | 2 | $9,913.11 | -13.5% | 6 |
| 06 | 1 | $13,779.00 | +20.2% | 2 |
| 07 | 2 | $12,615.00 | +10% | 14 |
| 08 | 7 | $19,302.85 | +68.4% | 24 |
| 09 | 1 | $6,600.00 | -42.4% | 1 |
| 10 | 2 | $7,016.67 | -38.8% | 3 |
| 12 | 5 | $7,241.87 | -36.8% | 41 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0641 2 80 (Prestressed Concrete Pole, Complete Pole Removal- Pole 30' AND Greater) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 21 contracts with a quantity-weighted average of $11,463.97 per EA, on 93 EA worth $1,066,150 in total.
The same report run for earlier periods shows $8,576.49 in 2024 (28 contracts, 121 EA), $9,740.48 in 2025 (25 contracts, 139 EA), $11,463.97 in the latest 12 months (21 contracts, 93 EA). From 2024 to the latest 12 months the weighted average rose 33.7%.
Quantity let statewide shrank 23% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 01 at $7,334.00 (1 contract), area 05 at $9,913.11 (2 contracts), area 06 at $13,779.00 (1 contract), area 07 at $12,615.00 (2 contracts), area 08 at $19,302.85 (7 contracts), area 09 at $6,600.00 (1 contract), area 10 at $7,016.67 (2 contracts), area 12 at $7,241.87 (5 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0641: 0641 2 12 Prestressed Concrete Pole, F&I, Type P-II Service Pole ($2,585.82 per EA, 102 contracts); 0641 2 60 Prestressed Concrete Pole, Complete Pole Removal- Pedestal/Service Pole ($870.82 per EA, 47 contracts); 0641 2 70 Prestressed Concrete Pole, Shallow Pole Removal- Pole 30' AND Greater ($4,726.84 per EA, 16 contracts); 0641 3163 Concrete Cctv Pole, Furnish & Install With Lowering Device, 63' ($41,820.81 per EA, 9 contracts); 0641 2 11 Prestressed Concrete Pole, F&I, Type P-II Pedestal ($2,379.71 per EA, 8 contracts).
Related items in section 0641
- 0641 2 12 · Prestressed Concrete Pole, F&I, Type P-II Service Pole ($2,585.82/EA)
- 0641 2 60 · Prestressed Concrete Pole, Complete Pole Removal- Pedestal/Service Pole ($870.82/EA)
- 0641 2 70 · Prestressed Concrete Pole, Shallow Pole Removal- Pole 30' AND Greater ($4,726.84/EA)
- 0641 3163 · Concrete Cctv Pole, Furnish & Install With Lowering Device, 63' ($41,820.81/EA)
- 0641 2 11 · Prestressed Concrete Pole, F&I, Type P-II Pedestal ($2,379.71/EA)
- 0641 3186 · Concrete Cctv Pole, Furnish & Install With Lowering Device, 86' ($48,085.99/EA)
- 0641 3169 · Concrete Cctv Pole, Furnish & Install With Lowering Device, 69' ($38,830.36/EA)
- 0641 3175 · Concrete Cctv Pole, Furnish & Install With Lowering Device, 75' ($49,732.31/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.