Prestressed Concrete Pole, F&I, Type P-II Service Pole (Item 0641 2 12): FDOT Unit Price History

102 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$2,585.82/EA
Contracts (12 mo)
102
Total quantity (12 mo)
410 EA
Total amount (12 mo)
$1,060,187

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-31135$2,714.59673$1,826,921
20252025-01-01 – 2025-12-31128$2,755.31742$2,044,440
Latest 12 months2025-11-01 – 2026-10-31102$2,585.82410$1,060,187

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
015$2,660.00+2.9%5
022$2,730.98+5.6%4
034$2,718.45+5.1%9
041$2,752.79+6.5%2
054$1,505.56-41.8%17
067$2,586.000%44
078$2,102.95-18.7%27
0821$2,967.50+14.8%82
107$2,106.27-18.5%21
115$2,382.30-7.9%14
1220$2,548.71-1.4%97
1313$2,856.80+10.5%70

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0641 2 12 (Prestressed Concrete Pole, F&I, Type P-II Service Pole) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 102 contracts with a quantity-weighted average of $2,585.82 per EA, on 410 EA worth $1,060,187 in total.

The same report run for earlier periods shows $2,714.59 in 2024 (135 contracts, 673 EA), $2,755.31 in 2025 (128 contracts, 742 EA), $2,585.82 in the latest 12 months (102 contracts, 410 EA). From 2024 to the latest 12 months the weighted average fell 4.7%.

Quantity let statewide shrank 39% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 10 market areas with at least three contracts, market area 05 had the lowest weighted average ($1,505.56 per EA, 4 contracts) and market area 08 the highest ($2,967.50, 21 contracts), 2.0 times as much. Market area 08 let the most contracts with this item (21). 12 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0641: 0641 2 60 Prestressed Concrete Pole, Complete Pole Removal- Pedestal/Service Pole ($870.82 per EA, 47 contracts); 0641 2 80 Prestressed Concrete Pole, Complete Pole Removal- Pole 30' AND Greater ($11,463.97 per EA, 21 contracts); 0641 2 70 Prestressed Concrete Pole, Shallow Pole Removal- Pole 30' AND Greater ($4,726.84 per EA, 16 contracts); 0641 3163 Concrete Cctv Pole, Furnish & Install With Lowering Device, 63' ($41,820.81 per EA, 9 contracts); 0641 2 11 Prestressed Concrete Pole, F&I, Type P-II Pedestal ($2,379.71 per EA, 8 contracts).

Related items in section 0641

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.