Fiber Reinforced Polymer Bars, #5 BAR (Item 0415 10 5): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $2.57/LF
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 217,763 LF
- Total amount (12 mo)
- $559,741
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 2 | $3.84 | 154,878 | $594,408 |
| 2025 | 2025-01-01 – 2025-12-31 | 9 | $3.15 | 248,426 | $783,653 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $2.57 | 217,763 | $559,741 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 02 | 2 | $2.83 | +10.1% | 10,586 |
| 03 | 1 | $2.54 | -1.2% | 34,317 |
| 04 | 1 | $2.65 | +3.1% | 56,074 |
| 05 | 2 | $2.52 | -1.9% | 68,290 |
| 07 | 1 | $1.70 | -33.9% | 3,470 |
| 10 | 1 | $6.00 | +133.5% | 7,974 |
| 11 | 1 | $1.65 | -35.8% | 31,727 |
| 13 | 1 | $3.00 | +16.7% | 5,325 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0415 10 5 (Fiber Reinforced Polymer Bars, #5 BAR) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $2.57 per LF, on 217,763 LF worth $559,741 in total.
The same report run for earlier periods shows $3.84 in 2024 (2 contracts, 154,878 LF), $3.15 in 2025 (9 contracts, 248,426 LF), $2.57 in the latest 12 months (10 contracts, 217,763 LF). From 2024 to the latest 12 months the weighted average fell 33.1%.
Quantity let statewide grew 41% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 02 at $2.83 (2 contracts), area 03 at $2.54 (1 contract), area 04 at $2.65 (1 contract), area 05 at $2.52 (2 contracts), area 07 at $1.70 (1 contract), area 10 at $6.00 (1 contract), area 11 at $1.65 (1 contract), area 13 at $3.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0415: 0415 1 5 Reinforcing Steel- Bridge Substructure ($1.56 per LB, 29 contracts); 0415 1 4 Reinforcing Steel - Bridge Superstructure ($1.51 per LB, 28 contracts); 0415 1 9 Reinforcing Steel- Approach Slabs ($1.57 per LB, 28 contracts); 0415 1 1 Reinforcing Steel- Roadway ($1.04 per LB, 15 contracts); 0415 1 3 Reinforcing Steel- Retaining Wall ($1.52 per LB, 8 contracts).
Related items in section 0415
- 0415 1 5 · Reinforcing Steel- Bridge Substructure ($1.56/LB)
- 0415 1 4 · Reinforcing Steel - Bridge Superstructure ($1.51/LB)
- 0415 1 9 · Reinforcing Steel- Approach Slabs ($1.57/LB)
- 0415 1 1 · Reinforcing Steel- Roadway ($1.04/LB)
- 0415 1 3 · Reinforcing Steel- Retaining Wall ($1.52/LB)
- 0415 1 8 · Reinforcing Steel- Bulkhead ($1.94/LB)
- 0415 1 6 · Reinforcing Steel- Miscellaneous ($3.47/LB)
- 0415 10 4 · Fiber Reinforced Polymer Bars, #4 BAR ($2.38/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.