Reinforcing Steel- Roadway (Item 0415 1 1): FDOT Unit Price History
15 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LB
- Weighted average (12 mo)
- $1.04/LB
- Contracts (12 mo)
- 15
- Total quantity (12 mo)
- 753,163 LB
- Total amount (12 mo)
- $780,371
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 11 | $0.260 | 3,129,282 | $809,387 |
| 2025 | 2025-01-01 – 2025-12-31 | 9 | $0.480 | 2,723,393 | $1,297,039 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 15 | $1.04 | 753,163 | $780,371 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $1.20 | +15.4% | 44,388 |
| 02 | 2 | $2.37 | +127.9% | 60,342 |
| 04 | 2 | $1.08 | +3.8% | 157,300 |
| 06 | 1 | $4.75 | +356.7% | 921 |
| 07 | 2 | $0.720 | -30.8% | 234,743 |
| 08 | 3 | $2.80 | +169.2% | 36,118 |
| 09 | 1 | $1.75 | +68.3% | 71,069 |
| 12 | 2 | $0.110 | -89.4% | 148,282 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0415 1 1 (Reinforcing Steel- Roadway) is measured in LB. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 15 contracts with a quantity-weighted average of $1.04 per LB, on 753,163 LB worth $780,371 in total.
The same report run for earlier periods shows $0.260 in 2024 (11 contracts, 3,129,282 LB), $0.480 in 2025 (9 contracts, 2,723,393 LB), $1.04 in the latest 12 months (15 contracts, 753,163 LB). From 2024 to the latest 12 months the weighted average rose 300.0%.
Quantity let statewide shrank 76% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 01 at $1.20 (2 contracts), area 02 at $2.37 (2 contracts), area 04 at $1.08 (2 contracts), area 06 at $4.75 (1 contract), area 07 at $0.720 (2 contracts), area 08 at $2.80 (3 contracts), area 09 at $1.75 (1 contract), area 12 at $0.110 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0415: 0415 1 5 Reinforcing Steel- Bridge Substructure ($1.56 per LB, 29 contracts); 0415 1 4 Reinforcing Steel - Bridge Superstructure ($1.51 per LB, 28 contracts); 0415 1 9 Reinforcing Steel- Approach Slabs ($1.57 per LB, 28 contracts); 0415 10 5 Fiber Reinforced Polymer Bars, #5 BAR ($2.57 per LF, 10 contracts); 0415 1 3 Reinforcing Steel- Retaining Wall ($1.52 per LB, 8 contracts).
Related items in section 0415
- 0415 1 5 · Reinforcing Steel- Bridge Substructure ($1.56/LB)
- 0415 1 4 · Reinforcing Steel - Bridge Superstructure ($1.51/LB)
- 0415 1 9 · Reinforcing Steel- Approach Slabs ($1.57/LB)
- 0415 10 5 · Fiber Reinforced Polymer Bars, #5 BAR ($2.57/LF)
- 0415 1 3 · Reinforcing Steel- Retaining Wall ($1.52/LB)
- 0415 1 8 · Reinforcing Steel- Bulkhead ($1.94/LB)
- 0415 1 6 · Reinforcing Steel- Miscellaneous ($3.47/LB)
- 0415 10 4 · Fiber Reinforced Polymer Bars, #4 BAR ($2.38/LF)