Reinforcing Steel- Bridge Substructure (Item 0415 1 5): FDOT Unit Price History
29 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LB
- Weighted average (12 mo)
- $1.56/LB
- Contracts (12 mo)
- 29
- Total quantity (12 mo)
- 6,042,202 LB
- Total amount (12 mo)
- $9,403,554
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 21 | $1.41 | 4,226,680 | $5,938,972 |
| 2025 | 2025-01-01 – 2025-12-31 | 39 | $1.58 | 6,847,500 | $10,811,977 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 29 | $1.56 | 6,042,202 | $9,403,554 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 6 | $1.91 | +22.4% | 86,575 |
| 02 | 2 | $2.00 | +28.2% | 42,731 |
| 03 | 3 | $2.63 | +68.6% | 75,901 |
| 04 | 1 | $3.50 | +124.4% | 15,213 |
| 05 | 1 | $3.96 | +153.8% | 4,942 |
| 07 | 3 | $1.35 | -13.5% | 842,428 |
| 08 | 3 | $2.77 | +77.6% | 100,735 |
| 09 | 1 | $1.13 | -27.6% | 7,037 |
| 10 | 1 | $1.40 | -10.3% | 3,129,841 |
| 11 | 1 | $1.70 | +9% | 968,613 |
| 12 | 5 | $1.73 | +10.9% | 671,999 |
| 13 | 2 | $2.75 | +76.3% | 96,187 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0415 1 5 (Reinforcing Steel- Bridge Substructure) is measured in LB. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 29 contracts with a quantity-weighted average of $1.56 per LB, on 6,042,202 LB worth $9,403,554 in total.
The same report run for earlier periods shows $1.41 in 2024 (21 contracts, 4,226,680 LB), $1.58 in 2025 (39 contracts, 6,847,500 LB), $1.56 in the latest 12 months (29 contracts, 6,042,202 LB). From 2024 to the latest 12 months the weighted average rose 10.6%.
Quantity let statewide grew 43% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 5 market areas with at least three contracts, market area 07 had the lowest weighted average ($1.35 per LB, 3 contracts) and market area 08 the highest ($2.77, 3 contracts), 2.1 times as much. Market area 01 let the most contracts with this item (6). 12 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0415: 0415 1 4 Reinforcing Steel - Bridge Superstructure ($1.51 per LB, 28 contracts); 0415 1 9 Reinforcing Steel- Approach Slabs ($1.57 per LB, 28 contracts); 0415 1 1 Reinforcing Steel- Roadway ($1.04 per LB, 15 contracts); 0415 10 5 Fiber Reinforced Polymer Bars, #5 BAR ($2.57 per LF, 10 contracts); 0415 1 3 Reinforcing Steel- Retaining Wall ($1.52 per LB, 8 contracts).
Related items in section 0415
- 0415 1 4 · Reinforcing Steel - Bridge Superstructure ($1.51/LB)
- 0415 1 9 · Reinforcing Steel- Approach Slabs ($1.57/LB)
- 0415 1 1 · Reinforcing Steel- Roadway ($1.04/LB)
- 0415 10 5 · Fiber Reinforced Polymer Bars, #5 BAR ($2.57/LF)
- 0415 1 3 · Reinforcing Steel- Retaining Wall ($1.52/LB)
- 0415 1 8 · Reinforcing Steel- Bulkhead ($1.94/LB)
- 0415 1 6 · Reinforcing Steel- Miscellaneous ($3.47/LB)
- 0415 10 4 · Fiber Reinforced Polymer Bars, #4 BAR ($2.38/LF)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.