Concrete Class IV, Mass, Substructure (Item 0400 4 25): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure CY
- Weighted average (12 mo)
- $1,712.38/CY
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 18,033.2 CY
- Total amount (12 mo)
- $30,879,665
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 8 | $1,375.23 | 11,885.1 | $16,344,803 |
| 2025 | 2025-01-01 – 2025-12-31 | 17 | $1,871.12 | 15,060.8 | $28,180,634 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $1,712.38 | 18,033.2 | $30,879,665 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $2,936.42 | +71.5% | 120.7 |
| 07 | 2 | $2,064.67 | +20.6% | 1,753.6 |
| 08 | 2 | $2,061.87 | +20.4% | 125.2 |
| 10 | 1 | $1,500.00 | -12.4% | 10,023 |
| 11 | 1 | $2,000.00 | +16.8% | 3,498.8 |
| 12 | 4 | $1,439.26 | -15.9% | 1,570 |
| 13 | 1 | $2,500.00 | +46% | 941.9 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0400 4 25 (Concrete Class IV, Mass, Substructure) is measured in CY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $1,712.38 per CY, on 18,033.2 CY worth $30,879,665 in total.
The same report run for earlier periods shows $1,375.23 in 2024 (8 contracts, 11,885.1 CY), $1,871.12 in 2025 (17 contracts, 15,060.8 CY), $1,712.38 in the latest 12 months (12 contracts, 18,033.2 CY). From 2024 to the latest 12 months the weighted average rose 24.5%.
Quantity let statewide grew 52% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $2,936.42 (1 contract), area 07 at $2,064.67 (2 contracts), area 08 at $2,061.87 (2 contracts), area 10 at $1,500.00 (1 contract), area 11 at $2,000.00 (1 contract), area 12 at $1,439.26 (4 contracts), area 13 at $2,500.00 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0400: 0400 0 11 Concrete Class NS, Gravity Wall Index 400-011 ($898.26 per CY, 34 contracts); 0400 4 5 Concrete Class IV, Bridge Substructure ($2,444.33 per CY, 29 contracts); 0400 2 10 Concrete Class II, Approach Slabs ($963.60 per CY, 28 contracts); 0400 7 1 Bridge Deck Grooving ($7.59 per SY, 24 contracts); 0400 9 1 Bridge Deck Planing ($7.78 per SY, 18 contracts).
Related items in section 0400
- 0400 0 11 · Concrete Class NS, Gravity Wall Index 400-011 ($898.26/CY)
- 0400 4 5 · Concrete Class IV, Bridge Substructure ($2,444.33/CY)
- 0400 2 10 · Concrete Class II, Approach Slabs ($963.60/CY)
- 0400 7 1 · Bridge Deck Grooving ($7.59/SY)
- 0400 9 1 · Bridge Deck Planing ($7.78/SY)
- 0400 2 4 · Conc Class II, Bridge Superstructure ($1,387.01/CY)
- 0400 4 1 · Concrete Class IV, Culverts ($2,139.81/CY)
- 0400 4 8 · Conc Class IV, Bulkhead ($1,706.13/CY)