Concrete Class IV, Culverts (Item 0400 4 1): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure CY
- Weighted average (12 mo)
- $2,139.81/CY
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 3,079.1 CY
- Total amount (12 mo)
- $6,588,699
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 6 | $2,156.56 | 14,877.2 | $32,083,582 |
| 2025 | 2025-01-01 – 2025-12-31 | 11 | $1,725.47 | 14,148.1 | $24,412,162 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $2,139.81 | 3,079.1 | $6,588,699 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 3 | $2,488.88 | +16.3% | 284.5 |
| 02 | 3 | $2,371.59 | +10.8% | 529.7 |
| 04 | 1 | $2,226.09 | +4% | 473.6 |
| 07 | 1 | $1,900.00 | -11.2% | 585.4 |
| 08 | 1 | $2,300.00 | +7.5% | 124 |
| 09 | 1 | $1,525.00 | -28.7% | 403 |
| 12 | 2 | $2,294.99 | +7.3% | 678.9 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0400 4 1 (Concrete Class IV, Culverts) is measured in CY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $2,139.81 per CY, on 3,079.1 CY worth $6,588,699 in total.
The same report run for earlier periods shows $2,156.56 in 2024 (6 contracts, 14,877.2 CY), $1,725.47 in 2025 (11 contracts, 14,148.1 CY), $2,139.81 in the latest 12 months (12 contracts, 3,079.1 CY). Across those periods the weighted average stayed within three percent.
Quantity let statewide shrank 79% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 01 at $2,488.88 (3 contracts), area 02 at $2,371.59 (3 contracts), area 04 at $2,226.09 (1 contract), area 07 at $1,900.00 (1 contract), area 08 at $2,300.00 (1 contract), area 09 at $1,525.00 (1 contract), area 12 at $2,294.99 (2 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0400: 0400 0 11 Concrete Class NS, Gravity Wall Index 400-011 ($898.26 per CY, 34 contracts); 0400 4 5 Concrete Class IV, Bridge Substructure ($2,444.33 per CY, 29 contracts); 0400 2 10 Concrete Class II, Approach Slabs ($963.60 per CY, 28 contracts); 0400 7 1 Bridge Deck Grooving ($7.59 per SY, 24 contracts); 0400 9 1 Bridge Deck Planing ($7.78 per SY, 18 contracts).
Related items in section 0400
- 0400 0 11 · Concrete Class NS, Gravity Wall Index 400-011 ($898.26/CY)
- 0400 4 5 · Concrete Class IV, Bridge Substructure ($2,444.33/CY)
- 0400 2 10 · Concrete Class II, Approach Slabs ($963.60/CY)
- 0400 7 1 · Bridge Deck Grooving ($7.59/SY)
- 0400 9 1 · Bridge Deck Planing ($7.78/SY)
- 0400 2 4 · Conc Class II, Bridge Superstructure ($1,387.01/CY)
- 0400 4 25 · Concrete Class IV, Mass, Substructure ($1,712.38/CY)
- 0400 4 8 · Conc Class IV, Bulkhead ($1,706.13/CY)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.