Floating Turbidity Barrier (Item 0104 11): FDOT Unit Price History
74 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $14.15/LF
- Contracts (12 mo)
- 74
- Total quantity (12 mo)
- 98,552 LF
- Total amount (12 mo)
- $1,394,966
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 78 | $9.09 | 156,704 | $1,424,208 |
| 2025 | 2025-01-01 – 2025-12-31 | 75 | $16.38 | 86,365 | $1,415,035 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 74 | $14.15 | 98,552 | $1,394,966 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 8 | $14.34 | +1.3% | 9,556 |
| 02 | 7 | $13.31 | -5.9% | 2,960 |
| 03 | 5 | $15.07 | +6.5% | 2,566 |
| 04 | 5 | $24.07 | +70.1% | 2,646 |
| 05 | 3 | $17.97 | +27% | 3,525 |
| 06 | 1 | $25.00 | +76.7% | 31 |
| 07 | 7 | $12.63 | -10.7% | 8,330 |
| 08 | 14 | $18.00 | +27.2% | 9,056 |
| 09 | 4 | $12.67 | -10.5% | 1,428 |
| 10 | 3 | $10.19 | -28% | 28,133 |
| 11 | 2 | $12.36 | -12.7% | 2,790 |
| 12 | 10 | $21.72 | +53.5% | 12,887 |
| 13 | 3 | $43.11 | +204.7% | 1,580 |
| 14 | 1 | $8.50 | -39.9% | 3,384 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0104 11 (Floating Turbidity Barrier) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 74 contracts with a quantity-weighted average of $14.15 per LF, on 98,552 LF worth $1,394,966 in total.
The same report run for earlier periods shows $9.09 in 2024 (78 contracts, 156,704 LF), $16.38 in 2025 (75 contracts, 86,365 LF), $14.15 in the latest 12 months (74 contracts, 98,552 LF). From 2024 to the latest 12 months the weighted average rose 55.7%.
Quantity let statewide shrank 37% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 11 market areas with at least three contracts, market area 10 had the lowest weighted average ($10.19 per LF, 3 contracts) and market area 13 the highest ($43.11, 3 contracts), 4.2 times as much. Market area 08 let the most contracts with this item (14). 14 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0104: 0104 18 Inlet Protection System ($170.49 per EA, 204 contracts); 0104 10 3 Sediment Barrier ($2.17 per LF, 197 contracts); 0104 15 Soil Tracking Prevention Device ($3,814.24 per EA, 65 contracts); 0104 12 Staked Turbidity Barrier- Nylon Reinforced PVC ($8.74 per LF, 49 contracts); 0104 1 Artificial Coverings /Rolled Erosion Control Products ($6.58 per SY, 28 contracts).
Related items in section 0104
- 0104 18 · Inlet Protection System ($170.49/EA)
- 0104 10 3 · Sediment Barrier ($2.17/LF)
- 0104 15 · Soil Tracking Prevention Device ($3,814.24/EA)
- 0104 12 · Staked Turbidity Barrier- Nylon Reinforced PVC ($8.74/LF)
- 0104 1 · Artificial Coverings /Rolled Erosion Control Products ($6.58/SY)
- 0104 19 · Chemical Treatment- Powdered, FOR Erosion Control ($46.03/SY)
- 0104 6 · Temporary Slope Drain / Runoff Control Structure ($68.53/LF)
- 0104 7 · Sediment Basin / Containment System ($4,330.00/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.