Artificial Coverings /Rolled Erosion Control Products (Item 0104 1): FDOT Unit Price History
28 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure SY
- Weighted average (12 mo)
- $6.58/SY
- Contracts (12 mo)
- 28
- Total quantity (12 mo)
- 13,503 SY
- Total amount (12 mo)
- $88,833
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 26 | $8.07 | 46,692 | $377,026 |
| 2025 | 2025-01-01 – 2025-12-31 | 15 | $5.60 | 59,623 | $333,632 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 28 | $6.58 | 13,503 | $88,833 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 5 | $13.09 | +98.9% | 903 |
| 02 | 1 | $45.00 | +583.9% | 11 |
| 03 | 2 | $4.96 | -24.6% | 4,517 |
| 04 | 3 | $4.75 | -27.8% | 1,365 |
| 05 | 3 | $4.96 | -24.6% | 450 |
| 06 | 2 | $42.55 | +546.7% | 29 |
| 07 | 5 | $8.52 | +29.5% | 931 |
| 08 | 6 | $6.26 | -4.9% | 1,168 |
| 13 | 1 | $7.00 | +6.4% | 4,129 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0104 1 (Artificial Coverings /Rolled Erosion Control Products) is measured in SY. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 28 contracts with a quantity-weighted average of $6.58 per SY, on 13,503 SY worth $88,833 in total.
The same report run for earlier periods shows $8.07 in 2024 (26 contracts, 46,692 SY), $5.60 in 2025 (15 contracts, 59,623 SY), $6.58 in the latest 12 months (28 contracts, 13,503 SY). From 2024 to the latest 12 months the weighted average fell 18.5%.
Quantity let statewide shrank 71% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 5 market areas with at least three contracts, market area 04 had the lowest weighted average ($4.75 per SY, 3 contracts) and market area 01 the highest ($13.09, 5 contracts), 2.8 times as much. Market area 08 let the most contracts with this item (6). 9 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0104: 0104 18 Inlet Protection System ($170.49 per EA, 204 contracts); 0104 10 3 Sediment Barrier ($2.17 per LF, 197 contracts); 0104 11 Floating Turbidity Barrier ($14.15 per LF, 74 contracts); 0104 15 Soil Tracking Prevention Device ($3,814.24 per EA, 65 contracts); 0104 12 Staked Turbidity Barrier- Nylon Reinforced PVC ($8.74 per LF, 49 contracts).
Related items in section 0104
- 0104 18 · Inlet Protection System ($170.49/EA)
- 0104 10 3 · Sediment Barrier ($2.17/LF)
- 0104 11 · Floating Turbidity Barrier ($14.15/LF)
- 0104 15 · Soil Tracking Prevention Device ($3,814.24/EA)
- 0104 12 · Staked Turbidity Barrier- Nylon Reinforced PVC ($8.74/LF)
- 0104 19 · Chemical Treatment- Powdered, FOR Erosion Control ($46.03/SY)
- 0104 6 · Temporary Slope Drain / Runoff Control Structure ($68.53/LF)
- 0104 7 · Sediment Basin / Containment System ($4,330.00/EA)