Zachry Construction Corporation: TxDOT Bid Results and Margins

Name as published by TxDOT: ZACHRY CONSTRUCTION CORPORATION · Data as published by TxDOT, lettings Mar 4, 2025 to Nov 4, 2026, retrieved Nov 24, 2026.

Proposals bid
24
Low bids (rank 1)
1
Win rate
4.17%
Low-bid value
$123.5M
Money left on table
$7.5M
Avg. bid vs. estimate
+3.97%

From Mar 4, 2025 to Nov 4, 2026, Zachry Construction Corporation submitted 24 bids on TxDOT proposals and was the apparent low bidder on 1 of them (4.17%), with low bids totalling $123,539,232. In 1 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $7,515,942 (6.08% of those bids); the median gap was 6.08%. On average its bids came in 3.97% above TxDOT's engineer's estimate. Its most frequent district was Dallas (7 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20258112.5%$123,539,232
20261600.0%$0

Head-to-head rivals

BidderProposals togetherRanked ahead
Webber, LLC204 of 20
Pulice Construction, Inc.123 of 12
James Construction Group, LLC91 of 9
Granite Construction Company85 of 8
Posillico Civil, Inc.81 of 8
Indus Road & Bridge, Inc.72 of 7
Mario Sinacola & Sons Excavating, Inc.73 of 7
Austin Bridge & Road Services, LP63 of 6

Districts and work types

DistrictBids
Dallas7
Houston4
San Antonio4
Austin2
Laredo2
Work type of low bidsLow bids
Interchange (New or Reconstructed)1

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-040195-02-092DentonWiden Freeway6 of 6$154,873,429+12.1%+7.3%
2026-11-040212-03-058BrazosBridge Replacement9 of 12$42,444,061+40.5%+33.8%
2026-10-060095-03-100KaufmanBridge Replacement5 of 10$64,858,828+17.9%-58.3%
2026-08-060018-05-089WebbInterchange (New or Reconstructed)4 of 4$274,867,526+33.6%+21.2%
2026-08-050027-08-147Fort BendWiden Non-Freeway3 of 7$49,951,826+2.3%-4.8%
2026-07-020914-04-377TravisTransportation Non-Roadway5 of 6$22,146,359+184.7%+35.8%
2026-07-021502-01-031LubbockConvert Non-Freeway To Freeway4 of 5$276,846,375+24.9%-6.7%
2026-07-012452-03-128BexarWiden Freeway6 of 7$194,747,209+16.1%+11.1%
2026-07-013510-04-066Fort BendNew Location Non-Freeway7 of 11$21,656,182+11%+7.7%
2026-06-020018-06-185WebbInterchange (New or Reconstructed)5 of 6$85,984,574+23.1%+28.7%
2026-05-060081-03-047DentonWiden Non-Freeway8 of 9$135,215,129+21.4%+21.2%
2026-04-080179-09-041JacksonBridge Replacement4 of 10$37,617,685+76.7%-4.7%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.