Wright Asphalt Products Company LLC: TxDOT Bid Results and Margins

Name as published by TxDOT: WRIGHT ASPHALT PRODUCTS COMPANY LLC · Data as published by TxDOT, lettings Nov 26, 2024 to Oct 13, 2026, retrieved Nov 24, 2026.

Proposals bid
70
Low bids (rank 1)
32
Win rate
45.71%
Low-bid value
$13.3M
Money left on table
$1.3M
Avg. bid vs. estimate
+8.38%

From Nov 26, 2024 to Oct 13, 2026, Wright Asphalt Products Company LLC submitted 70 bids on TxDOT proposals and was the apparent low bidder on 32 of them (45.71%), with low bids totalling $13,326,923. In 30 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $1,301,816 (10.55% of those bids); the median gap was 8.19%. On average its bids came in 8.38% above TxDOT's engineer's estimate. Its most frequent district was Bryan (14 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
202422100.0%$968,400
2025332060.6%$8,654,944
2026351028.6%$3,703,579

Head-to-head rivals

BidderProposals togetherRanked ahead
Ergon Asphalt & Emulsions, Inc.5524 of 55
Martin Resource Management Corporation3119 of 31
Cleveland Asphalt Products, Inc.1111 of 11
Southern Sourcing Solutions, LLC11 of 1

Districts and work types

DistrictBids
Bryan14
Lubbock10
Dallas9
Amarillo6
Odessa6
Work type of low bidsLow bids
Material Maintenance Project31
Material Maintenance Project - Sealed1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2025-01-076473-33-001LimestoneErgon Asphalt & Emulsions, Inc.$1,092,050$1,093,375+0.1%
2026-09-096502-14-001DentonErgon Asphalt & Emulsions, Inc.$142,560$143,100+0.4%
2025-04-176477-92-001HopkinsMartin Resource Management Corporation$428,050$431,250+0.8%
2025-04-086481-76-001WashingtonMartin Resource Management Corporation$84,240$85,200+1.1%
2025-02-076476-41-001WichitaErgon Asphalt & Emulsions, Inc.$1,044,600$1,063,700+1.8%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-10-136507-81-001BrazosMaterial Maintenance Project2 of 3$102,960+12.7%+15.9%
2026-09-166506-99-001WashingtonMaterial Maintenance Project2 of 3$103,200+12.9%+16.2%
2026-09-166507-16-001WashingtonMaterial Maintenance Project2 of 2$171,000+13.5%+1.8%
2026-09-166507-18-001WalkerMaterial Maintenance Project2 of 3$156,400+12.5%+1.8%
2026-09-156507-00-001WalkerMaterial Maintenance Project2 of 3$137,600+12%+16.2%
2026-09-156507-17-001FreestoneMaterial Maintenance Project2 of 3$114,000+13.5%+4.8%
2026-09-156508-35-001San SabaMaterial Maintenance Project2 of 3$93,600+5.3%-2.6%
2026-09-096502-14-001DentonMaterial Maintenance Project2 of 2$143,100+0.4%-8.3%
2026-09-096502-53-001NavarroMaterial Maintenance Project2 of 2$293,850+4.8%+10.5%
2026-08-126501-42-001CollinMaterial Maintenance Project1 of 2$148,529—+3.2%
2026-08-126501-46-001CollinMaterial Maintenance Project1 of 2$46,680—-16.3%
2026-08-116505-33-001MidlandMaterial Maintenance Project1 of 2$78,720—-4.6%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.