Cleveland Asphalt Products, Inc.: TxDOT Bid Results and Margins
Name as published by TxDOT: CLEVELAND ASPHALT PRODUCTS, INC. · Data as published by TxDOT, lettings Nov 19, 2024 to Oct 13, 2026, retrieved Nov 24, 2026.
- Proposals bid
- 18
- Low bids (rank 1)
- 7
- Win rate
- 38.89%
- Low-bid value
- $5M
- Money left on table
- —
- Avg. bid vs. estimate
- +13.36%
From Nov 19, 2024 to Oct 13, 2026, Cleveland Asphalt Products, Inc. submitted 18 bids on TxDOT proposals and was the apparent low bidder on 7 of them (38.89%), with low bids totalling $4,974,720. On average its bids came in 13.36% above TxDOT's engineer's estimate. Its most frequent district was Bryan (9 bids).
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
By year
| Year | Bids | Low bids | Win rate | Low-bid value |
|---|---|---|---|---|
| 2024 | 3 | 3 | 100.0% | $1,368,300 |
| 2025 | 5 | 1 | 20.0% | $866,030 |
| 2026 | 10 | 3 | 30.0% | $2,740,390 |
Head-to-head rivals
| Bidder | Proposals together | Ranked ahead |
|---|---|---|
| Wright Asphalt Products Company LLC | 11 | 0 of 11 |
| Martin Resource Management Corporation | 7 | 0 of 7 |
| Ergon Asphalt & Emulsions, Inc. | 6 | 0 of 6 |
Districts and work types
| District | Bids |
|---|---|
| Bryan | 9 |
| Lufkin | 6 |
| Beaumont | 1 |
| Brownwood | 1 |
| Paris | 1 |
| Work type of low bids | Low bids |
|---|---|
| Material Maintenance Project | 6 |
| Material Maintenance Project - Sealed | 1 |
Recent bids
| Let date | Proposal | County | Work type | Rank | Bid total | vs. low bid | vs. estimate |
|---|---|---|---|---|---|---|---|
| 2026-10-13 | 6507-81-001 | Brazos | Material Maintenance Project | 3 of 3 | $118,480 | +29.7% | +33.4% |
| 2026-09-16 | 6506-99-001 | Washington | Material Maintenance Project | 3 of 3 | $110,720 | +21.1% | +24.7% |
| 2026-09-16 | 6507-18-001 | Walker | Material Maintenance Project | 3 of 3 | $190,800 | +37.2% | +24.2% |
| 2026-09-15 | 6507-00-001 | Walker | Material Maintenance Project | 3 of 3 | $146,320 | +19.1% | +23.6% |
| 2026-09-15 | 6507-17-001 | Freestone | Material Maintenance Project | 3 of 3 | $134,200 | +33.7% | +23.3% |
| 2026-09-15 | 6508-35-001 | San Saba | Material Maintenance Project | 3 of 3 | $116,280 | +30.8% | +21% |
| 2026-06-11 | 6502-37-001 | Brazos | Material Maintenance Project | 3 of 3 | $287,000 | +21.9% | +41.5% |
| 2026-04-27 | 6498-47-001 | Sabine | Material Maintenance Project | 1 of 1 | $956,320 | — | +15.7% |
| 2026-04-27 | 6498-48-001 | San Augustine | Material Maintenance Project | 1 of 1 | $833,620 | — | +15.7% |
| 2026-04-27 | 6498-49-001 | Polk | Material Maintenance Project | 1 of 1 | $950,450 | — | +15.8% |
| 2025-09-16 | 6491-04-001 | Newton | Material Maintenance Project - Sealed | 1 of 1 | $866,030 | — | -2.4% |
| 2025-04-17 | 6477-92-001 | Hopkins | Material Maintenance Project - Sealed | 3 of 3 | $470,150 | +9.8% | -1.9% |
Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.