Skyline Construction Paving & Striping: TxDOT Bid Results and Margins
Name as published by TxDOT: SKYLINE CONSTRUCTION PAVING & STRIPING · Data as published by TxDOT, lettings Apr 9, 2025 to Nov 17, 2026, retrieved Nov 24, 2026.
Proposals bid
49
Low bids (rank 1)
6
Win rate
12.24%
Low-bid value
$3M
Money left on table
$425K
Avg. bid vs. estimate
+3.5%
From Apr 9, 2025 to Nov 17, 2026, Skyline Construction Paving & Striping submitted 49 bids on TxDOT proposals and was the apparent low bidder on 6 of them (12.24%), with low bids totalling $3,040,261. In 6 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $424,698 (13.97% of those bids); the median gap was 15.59%. On average its bids came in 3.5% above TxDOT's engineer's estimate. Its most frequent district was Atlanta (10 bids).
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.