Maldonado-Burkett, Llp: TxDOT Bid Results and Margins

Name as published by TxDOT: MALDONADO-BURKETT, LLP · Data as published by TxDOT, lettings Nov 7, 2024 to Aug 5, 2026, retrieved Nov 24, 2026.

Proposals bid
9
Low bids (rank 1)
1
Win rate
11.11%
Low-bid value
$730K
Money left on table
$190K
Avg. bid vs. estimate
+4.3%

From Nov 7, 2024 to Aug 5, 2026, Maldonado-Burkett, Llp submitted 9 bids on TxDOT proposals and was the apparent low bidder on 1 of them (11.11%), with low bids totalling $730,498. In 1 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $190,037 (26.01% of those bids); the median gap was 26.01%. On average its bids came in 4.3% above TxDOT's engineer's estimate. Its most frequent district was Corpus Christi (7 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20242150.0%$730,498
2025400.0%$0
2026300.0%$0

Head-to-head rivals

BidderProposals togetherRanked ahead
Third Coast Services LLC50 of 5
The Levy Company, LLC33 of 3
Traf-Tex, Inc.32 of 3
3lw Civil LLC21 of 2
Austin Traffic Signal Construction Co., Inc.20 of 2
Austin Traffic Signal Construction Co., LLC21 of 2
E-Z Bel Construction, LLC22 of 2
Highway Barricades and Services, LLC20 of 2

Districts and work types

DistrictBids
Corpus Christi7
Laredo1
Yoakum1
Work type of low bidsLow bids
Routine Maintenance Project - Sealed1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2025-05-020102-01-126NuecesThird Coast Services LLC$419,930$467,552+11.3%
2025-03-186480-97-001San PatricioHighway Barricades and Services, LLC$188,952$283,270+49.9%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-08-050237-06-054DuvalTraffic Control Devices3 of 7$828,773+6.3%-14.6%
2026-07-020617-02-080NuecesSafety Improvement Projects3 of 3$543,799+13.1%+0.2%
2026-03-176496-23-001NuecesRoutine Maintenance Project - Sealed3 of 6$500,006+20%-0.2%
2025-06-040074-10-008Live OakSafety Improvement Projects3 of 9$1,120,516+9.7%-11.5%
2025-05-020102-01-126NuecesSafety Improvement Projects2 of 6$467,552+11.3%-12.3%
2025-03-186480-97-001San PatricioRoutine Maintenance Project - Sealed2 of 2$283,270+49.9%+42.6%
2025-03-050916-35-232NuecesTraffic Control Devices5 of 5$422,253+25.9%+13%
2024-11-196475-87-001NuecesRoutine Maintenance Project - Sealed1 of 2$730,498—-2.5%
2024-11-070144-01-075VictoriaSafety Improvement Projects3 of 4$1,107,565+20.4%+24.1%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.