Proposals bid
14
Low bids (rank 1)
3
Win rate
21.43%
Low-bid value
$37.8M
Money left on table
$4.3M
Avg. bid vs. estimate
+2.47%

From Jan 8, 2025 to Aug 6, 2026, James Hamilton Construction Co. submitted 14 bids on TxDOT proposals and was the apparent low bidder on 3 of them (21.43%), with low bids totalling $37,811,005. In 3 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $4,262,624 (11.27% of those bids); the median gap was 10.5%. On average its bids came in 2.47% above TxDOT's engineer's estimate. Its most frequent district was Lubbock (8 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
202513323.1%$37,811,005
2026100.0%$0

Head-to-head rivals

BidderProposals togetherRanked ahead
A. L. Helmcamp, Inc.123 of 12
Jones Bros. Dirt & Paving Contractors, Inc.83 of 8
Kiewit Infrastructure South Co.75 of 7
Rk Hall, LLC73 of 7
Duininck, Inc.61 of 6
Fnf Construction, Inc.40 of 4
Ragle Construction, Inc.41 of 4
Ck Newberry, LLC30 of 3

Districts and work types

DistrictBids
Lubbock8
Odessa6
Work type of low bidsLow bids
Hazard Elimination & Safety1
Safety Improvement Projects1
Super-2 Highway1

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-08-060168-03-038ParmerRehabilitation of Existing Road5 of 5$12,539,274+28.4%+24.7%
2025-12-030906-00-256EctorSafety Improvement Projects3 of 9$8,714,547+4.2%-31.1%
2025-12-020354-04-044WinklerSuper-2 Highway5 of 5$32,481,346+33.1%+22.2%
2025-11-060354-04-041WinklerSuper-2 Highway6 of 6$40,903,479+45%+13.9%
2025-10-090380-04-025TerrySuper-2 Highway3 of 5$23,457,089+5.2%-15.7%
2025-10-080294-01-041GainesSafety Improvement Projects1 of 3$8,218,152—-7%
2025-09-050380-06-019DawsonOverlay6 of 9$21,430,036+25.1%-0.9%
2025-08-070461-09-023GainesHazard Elimination & Safety1 of 2$698,729—+1.7%
2025-07-020292-04-063WardRehabilitation of Existing Road6 of 7$22,914,347+32.6%+20.4%
2025-06-050005-04-083MartinRehabilitation of Existing Road5 of 5$17,192,543+51.9%+5.8%
2025-05-010052-01-043ParmerOverlay3 of 8$30,719,988+3.6%+6.3%
2025-03-050139-03-053ReevesOverlay5 of 6$14,136,357+36.3%+5.5%